Consider a Shortest Job First (SJF) CPU scheduler, with the following process workload: Process Arrival Time CPU Burst
P1 t 4
P2 t+2 6
P3 t+3 1
P4 t+6 2
P5 t+7 7
P6 t+9 3

Assume that the CPU is idle and there are no other processes in the ready queue when P1 enters the ready queue at time t. Determine the schedule of process execution, and compute the wait times and turnaround times for each of the six processes. Which of the following is a FALSE statement about the wait times and turnaround times of the processes?

a. P6 has a larger turnaround time than P4
b. P6 has a smaller turnaround time than P2
c. P5 has a larger turnaround time than P4
d. P5 has the largest wait time

ansver
Answers: 3

Other questions on the subject: Computers and Technology

image
Computers and Technology, 22.06.2019 15:50, minideeri
The file sales data. xlsx contains monthly sales amounts for 40 sales regions. write a sub that uses a for loop to color the interior of every other row (rows 3, 5, etc.) gray. color only the data area, columns a to m. (check the file colors in excel. xlsm to find a nice color of gray.)
Answers: 2
image
Computers and Technology, 22.06.2019 19:30, keke6361
When using a public computer or network, you should always
Answers: 2
image
Computers and Technology, 23.06.2019 04:31, tbt81
Type the correct answer in the box. spell all words correctly. the managing director of a company sends a christmas greeting to all his employees through the company email. which type of network does he use? he uses an
Answers: 1
image
Computers and Technology, 23.06.2019 18:00, taiyana74
Ramona enjoys her job because she is able to kids in an after school program. the work value ramona feels strongest about is a. leadership b. risk c. independence d. work with people select the best answer from the choices provided a b c d
Answers: 1
You know the right answer?
Consider a Shortest Job First (SJF) CPU scheduler, with the following process workload: Process Arr...

Questions in other subjects: