How network diagram help in scheduling a project? Draw activity network diagram as per given table and demonstrate its step (Forward pass, Backward pass and Critical path). Activity Duration (WEEK) Precedence
A Hardware selection 6 - B Software Design 4 - C Software coding 3 A
D Software Testing 4 B
E File Take_on 3 B
F Write User Manual 10 - G User Training 3 E, F
H Install and test 2 C, D

ansver
Answers: 2

Other questions on the subject: Computers and Technology

image
Computers and Technology, 21.06.2019 15:10, reyescarlosivan0
Match the terms in the hlookup syntax with their explanation. a. lookup value b. data table c. row index d. mode 1. name of the table that contains the value 2. specifies if an exact match must be found 3. value to be searched 4. name of the row that contains the value
Answers: 1
image
Computers and Technology, 21.06.2019 17:00, naomicervero
Which process would best represent the opposite of exhausting air from a system?
Answers: 2
image
Computers and Technology, 22.06.2019 08:00, luclaymom805
Aplan to budget time for studying and activities is referred to as a study routine. study habits. study skills. a study schedule.
Answers: 1
image
Computers and Technology, 22.06.2019 14:20, babyrocks7300
Consider a byte-addressable computer with 16mb of main memory, a cache capable of storing a total of 64kb of data and block size of 32 bytes. (a) how many bits in the memory address? (b) how many blocks are in the cache? (c) specify the format of the memory address, including names and sizes, when the cache is: 1. direct-mapped 2. 4-way set associative 3. fully associative
Answers: 2
You know the right answer?
How network diagram help in scheduling a project? Draw activity network diagram as per given table...

Questions in other subjects:

Konu
Mathematics, 26.10.2019 00:43
Konu
Mathematics, 26.10.2019 00:43