A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 2

Other questions on the subject: Computers and Technology

image
Computers and Technology, 23.06.2019 02:00, kelseybell5522
For a typical middle-income family, what is the estimated cost of raising a child to the age of 18? $145,500 $245,340 $304,340 $455,500
Answers: 1
image
Computers and Technology, 23.06.2019 02:00, kayladgranger
Which demographic challenge is europe currently experiencing? a. an aging and decreasing population b. a baby boomc. an unequal distribution between males and females d. a large group of teenagers moving through the school system(i chose a but i'm unsure)
Answers: 1
image
Computers and Technology, 23.06.2019 06:00, ashleyd198308
Respond to the following in three to five sentences. select the workplace skill, habit, or attitude described in this chapter that you believe is most important for being a successful employee.
Answers: 1
image
Computers and Technology, 23.06.2019 08:30, Bradgarner772
Based on your knowledge of a good network, describe what you think is a perfect network would be. what kind of information and resources could users share on this network. what would the network administrator do? what kind of communication would be used?
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...

Questions in other subjects: