A project consists of 8 activities. The activity completion times and the precedence relationships are as follows: Activity. Completion time Days. immediate predecessor activities.

A. 5 -
B. 7 -
C. 6 -
D. 3 A
E. 4 B, C
F. 2 C
G. 6 A, D
H. 5 E, F

1. Draw the network diagram using AON model notations:

2. What is the critical path?

3. Calculate: Early Start, Early finish, Late start, Late finish, slack, critical path.

4. What is the minimum time to complete the projects?

Please answer and thank you

ansver
Answers: 2

Other questions on the subject: Computers and Technology

image
Computers and Technology, 22.06.2019 08:00, luclaymom805
Aplan to budget time for studying and activities is referred to as a study routine. study habits. study skills. a study schedule.
Answers: 1
image
Computers and Technology, 22.06.2019 11:00, abelxoconda
Which are examples of note-taking tools? check all that recording devices sticky notes digital highlighters paper flags highlighting pens digital displays digital flags
Answers: 1
image
Computers and Technology, 22.06.2019 23:30, elizabethburkha
Which text format is this, "the text is transcribed exactly as it sounds and includes all the utterances of the speakers. "?
Answers: 2
image
Computers and Technology, 23.06.2019 05:30, savyblue1724707
Sally is editing her science report about living things. she needs to copy a paragraph from her original report. order the steps sally needs to do to copy the text to her new document.
Answers: 1
You know the right answer?
A project consists of 8 activities. The activity completion times and the precedence relationships a...

Questions in other subjects: