There is a 2 percent defect rate at a specific point in a production process. If an inspector is placed at this point, all the defects can be detected and eliminated. The inspector would cost $10 per hour and could inspect units in the process at the current production rate of 48 per hour.
If no inspector is hired and defects are allowed to pass this point, there is a cost of $11 per defective unit to correct the defects later on.
Assume that the line will operate at the same rate (i. e., the current production rate) regardless of whether the inspector is hired or not.
a. If an inspector is hired, what will be the inspection cost per unit? (Round your answer to 3 decimal places.)
Inspection cost per unit $
b. If an inspector is not hired, what will be the defective cost per unit? (Round your answer to 3 decimal places.)
Defective cost per unit $
c. Should an inspector be hired based on costs alone?
Answers: 2
Chemistry, 22.06.2019 04:00, dustinsampsin2486
14. many depressants reduce small muscle control, making it harder for a. you to steer b. your mind to consider complex problems c. the eye to scan, focus, or stay still d. the kidneys to filter alcohol out of the bloodstream
Answers: 3
There is a 2 percent defect rate at a specific point in a production process. If an inspector is pla...
Chemistry, 27.07.2019 07:00
History, 27.07.2019 07:00
Chemistry, 27.07.2019 07:00