Scorpion gulch & western railway is preparing to build a new line through rolling mountains. they have hired you to do some calculations for tunnels and bridges needed on the line. you set up a cartesian coordinate system with

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 00:50, BARRION1981
Hanna intends to give her granddaughter, melodee, her antique hat pin. this heirloom has been kept under lock and key in the wall vault in the library of hanna's house in virginia. the hat pin is currently the only item in the vault. when hanna is visiting melodee in connecticut, hanna gives melodee the only key to the vault. melodee is grateful for the present and excitedly accepts. in this situation has there been a completed gift?
Answers: 3
image
Business, 22.06.2019 01:00, Travon1418
Azster inc. recorded sales revenue for the year that ended december 31, 2014 as $67,000. interest revenue of $5,300 and expenses of $14,000 were also recorded for the same period. what is aster’s net profit or loss?
Answers: 3
image
Business, 22.06.2019 15:10, emilypzamora11
On december 31, 2013, coronado company issues 173,000 stock-appreciation rights to its officers entitling them to receive cash for the difference between the market price of its stock and a pre-established price of $10. the fair value of the sars is estimated to be $5 per sar on december 31, 2014; $2 on december 31, 2015; $10 on december 31, 2016; and $8 on december 31, 2017. the service period is 4 years, and the exercise period is 7 years. prepare a schedule that shows the amount of compensation expense allocable to each year affected by the stock-appreciation rights plan.
Answers: 2
image
Business, 23.06.2019 02:00, brennarfa
Suppose that a major city’s main thoroughfare, which is also an interstate highway, will be completely closed to traffic for two years, from january 2014 to december 2015, for reconstruction at a cost of $535 million. if the construction company were to keep the highway open for traffic during construction, the highway reconstruction project would take much longer and be more expensive. suppose that construction would take four years if the highway were kept open, at a total cost of $800 million. the state department of transportation had to make its decision in 2014, one year before the start of construction (so that the first payment was one year away). so the department of transportation had the following choices: (i) close the highway during construction, at an annual cost of $267.5 million per year for two years. (ii) keep the highway open during construction, at an annual cost of $200 million per year for four years. now suppose the interest rate is 80%. calculate the present value of the costs incurred under each plan.
Answers: 3
You know the right answer?
Scorpion gulch & western railway is preparing to build a new line through rolling mountains. th...

Questions in other subjects: