You are managing a project that has the following activities: - Activity A can start immediately and has an estimated duration of eight weeks.
- Activity B can also start immediately and has an estimated duration of seven weeks.
- Activity C can start after Activity A is completed and has an estimated duration of one week.
- Activity D can start after Activity B is completed and has an estimated duration of six weeks.
- Activity E can start after both Activities C and D are completed and has an estimated duration of seven weeks.
- Activity F can start after Activity D is completed and has an estimated duration of two weeks.
Your sponsor is very disappointed that the project is taking longer than he expected and asked you to shorten the project duration by at least two weeks. You decided to shorten Activity A first as it is not a very critical activity in the project and has the longest duration. What will be the impact of your decision?
a. It will create a new critical path.
b. It will shorten the duration of the project.
c. The project duration will be eighteen weeks now.
d. It will not shorten the duration of the project.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 10:20, alayciaruffin076
What two things do you consider when evaluating the time value of money
Answers: 1
image
Business, 23.06.2019 11:40, serellehunt
Anewspaper story on the effect of higher milk prices on the market for ice cream contained the following: "as a result [of the increase in milk prices], retail prices for ice cream are up 4 percent from last year. . and ice cream consumption is down 3 percent." source: john curran, "ice cream, they scream: milk fat costs drive up ice cream prices," associated press, july 23, 2001. based on the information given, what is the price elasticity of demand for ice cream?
Answers: 1
image
Business, 23.06.2019 13:30, mrashrafkotkaat
the social-cultural environment a firm operates in is constantly changing, and having a significant impact on marketing strategies. the change is so rapid and immense that some firms have created a new position in the organization to handle this change. which title best describes the new position described in the scenario?
Answers: 3
image
Business, 24.06.2019 00:50, diamonds5307
Which type of ics facility is used to temporarily position and account for personnel?
Answers: 3
You know the right answer?
You are managing a project that has the following activities: - Activity A can start immediately a...

Questions in other subjects:

Konu
Mathematics, 22.04.2021 07:50
Konu
Mathematics, 22.04.2021 07:50
Konu
Physics, 22.04.2021 07:50
Konu
Mathematics, 22.04.2021 07:50
Konu
Mathematics, 22.04.2021 07:50