All of the following activities are appropriate upon completion of risk response planning EXCEPT: a. The project plan should be updated to reflect any changes to the project schedule, budget or resource assignments. b. The risk register should be updated to reflect the risk response strategies. c. A single person should be assigned as the owner of each risk. d. The risk register should be baselined after planning is completed, and should not be updated once the project is in flight.

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 20:30, xojade
Which of the following actions would be most likely to reduce potential conflicts of interest between stockholders and bondholders? a) compensating managers with stock options, b) financing risky projects with additional debt, c) the threat of hostile takeovers, d) the use of covenants in bond agreements that limit the firm's use of additional debt and constrain managers actions, e) abolishing the security and exchange commission
Answers: 1
image
Business, 22.06.2019 17:40, makayladurham19
Slimwood corporation made sales of $ 725 million during 2018. of this amount, slimwood collected cash for $ 670 million. the company's cost of goods sold was $ 300 million, and all other expenses for the year totaled $ 400 million. also during 2018, slimwood paid $ 420 million for its inventory and $ 285 million for everything else. beginning cash was $ 110 million. carter's top management is interviewing you for a job and they ask two questions: (a) how much was carter's net income for 2018? (b) how much was carter's cash balance at the end of 2016? you will get the job only if you answer both questions correctly.
Answers: 1
image
Business, 22.06.2019 18:00, wirchakethan23
Match the different financial task to their corresponding financial life cycle phases
Answers: 3
image
Business, 22.06.2019 19:00, xojade
1. what must one do to perform the essential managerial task of controlling in achieving organizational goals? a. motivate, coordinate, and energize individuals and groups to work together to achieve organizational goals b. choose appropriate organizational goals and courses of action to best achieve those goals c. establish task and authority relationships that allow people to work together to achieve organizational goals d. establish accurate measuring and monitoring systems to evaluate how well the organization has achieved its goals
Answers: 1
You know the right answer?
All of the following activities are appropriate upon completion of risk response planning EXCEPT: a....

Questions in other subjects:

Konu
Mathematics, 06.05.2020 03:17