Business, 13.10.2021 23:10 gunaranjan09

A project has three sequences of activities (paths), two of which are critical. The critical paths of this project can be characterized in the following way: Group of answer choices The slack times for each task in the project are zero. The chain of activities (from start to finish) that has the largest sum of activity durations. The early start date and early finish date are always the same for each activity on the critical path. To reduce the project duration, you must reduce the slack time of a task on the critical path. Reducing a critical path will reduce the overall project duration

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 09:50, thanitoast84
Acar manufacturer uses new machines that automatically assemble an engine from parts fed to the system. the machine can regulate the speed ofassembly depending on the number of parts produced. which type of technology does this machine use? angenoem mense wat ons in matin en esta va ser elthe machine uses
Answers: 3
image
Business, 22.06.2019 13:30, CristianPaz
Presented below is information for annie company for the month of march 2018. cost of goods sold $245,000 rent expense $ 36,000 freight-out 7,000 sales discounts 8,000 insurance expense 5,000 sales returns and allowances 11,000 salaries and wages expense 63,000 sales revenue 410,000 instructions prepare the income statement.
Answers: 2
image
Business, 23.06.2019 08:20, vhuyrtyy
You are a newspaper publisher. you are in the middle of a one-year rental contract for your factory that requires you to pay $500,000 per month, and you have contractual labor obligations of $1 million per month that you can't get out of. you also have a marginal printing cost of $.25 per paper as well as a marginal delivery cost of $.10 per paper. if sales fall by 20 percent from 1 million papers per month to 800,000 papers per month, what happens to the afc per paper?
Answers: 2
image
Business, 23.06.2019 10:00, savannahvargas512
Top flight is a commuter airline service that provides short flights to neighboring citles around houston, texas. to determine the quantity of planes it will purchase, top flight needs to examine the for its flights at the prices it intends to charge and at the times it intends to flight. a. supply b. demand c. equilibrium price d. break-even point
Answers: 2
You know the right answer?
A project has three sequences of activities (paths), two of which are critical. The critical paths o...

Questions in other subjects:

Konu
Social Studies, 28.04.2021 06:40
Konu
Mathematics, 28.04.2021 06:40
Konu
Biology, 28.04.2021 06:40