A project has seven activities: A. B, C, D, E, F, and G. Activities A. B, and D can start anytime. Activity A takes 3 weeks. Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. What is the critical path

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 09:00, jamesgraham577
Afood worker has just rinsed a dish after cleaning it. what should he do next?
Answers: 2
image
Business, 22.06.2019 19:00, whitbol
The demand curve determines equilibrium price in a market. is a graphical representation of the relationship between price and quantity demanded. depicts the relationship between production costs and output. is a graphical representation of the relationship between price and quantity supplied.
Answers: 1
image
Business, 22.06.2019 19:10, jonmorton159
The stock of grommet corporation, a u. s. company, is publicly traded, with no single shareholder owning more than 5 percent of its outstanding stock. grommet owns 95 percent of the outstanding stock of staple inc., also a u. s. company. staple owns 100 percent of the outstanding stock of clip corporation, a canadian company. grommet and clip each own 50 percent of the outstanding stock of fastener inc., a u. s. company. grommet and staple each own 50 percent of the outstanding stock of binder corporation, a u. s. company. which of these corporations form an affiliated group eligible to file a consolidated tax return?
Answers: 3
image
Business, 22.06.2019 19:50, hdkdkdbx
Managers in a firm hired to improve the firm's profitability and ultimately the shareholders' value will add to the overall costs if they pursue their own self-interests. what does this best illustrate? a. diseconomies of scale b. principal-agent problem c. experience-curveeffects d. information asymmetries
Answers: 1
You know the right answer?
A project has seven activities: A. B, C, D, E, F, and G. Activities A. B, and D can start anytime. A...