Kingbird Construction Company began work on a $420,500 construction contract in 2020. During 2020, Kingbird incurred costs of $299,000, billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $151,030. Required:
Prepare Indigo’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 10:00, silviamgarcia
Scenario: you have advised the owner of bond's gym that the best thing to do would be to raise the price of a monthly membership. the owner wants to know what may happen once this price increase goes into effect. what will most likely occur after the price of a monthly membership increases? check all that apply. current members will pay more per month. the quantity demanded for memberships will decrease. the number of available memberships will increase. the owner will make more money. bond's gym will receive more membership applications.
Answers: 1
image
Business, 22.06.2019 13:10, KillerSteamcar
A4-year project has an annual operating cash flow of $59,000. at the beginning of the project, $5,000 in net working capital was required, which will be recovered at the end of the project. the firm also spent $23,900 on equipment to start the project. this equipment will have a book value of $5,260 at the end of the project, but can be sold for $6,120. the tax rate is 35 percent. what is the year 4 cash flow?
Answers: 2
image
Business, 22.06.2019 14:10, miacervenka
When paul o’neill joined alcoa as ceo, he set a , that there would be zero workplace accidents. a lot of people in the organization thought this was impossible given how dangerous some aluminum-manufacturing jobs are, but alcoa’s safety record improved tremendously. as the board of governors of the american red cross considers planning, one option is to make strategic plans and then direct managers to align tactical and operational plans accordingly. another option is to have planning specialists managers across the organization make their own plans. why might this organization’s executives opt for the latter approach? check all that apply. (a) the environment is a dynamic one, and department and frontline managers can come up with more responsive plans than can central leadership. (b)resources will be better coordinated across the organization in support of the overall strategy.(c) senior leadership will have more control over the organization’s direction. (d)when managers come up with their own plans, they are likely to be more committed to following through on them.
Answers: 2
image
Business, 22.06.2019 17:00, HourlongNine342
Serious question, which is preferred in a business? pp or poopoo?
Answers: 1
You know the right answer?
Kingbird Construction Company began work on a $420,500 construction contract in 2020. During 2020, K...