1- You are the Project Manager of a large project. One of your contractors sends you an email requesting to reduce the specification that requires ten tests be conducted down to only eight tests. What should you do first as the Project Manager? a- Change the scope baseline to require only 8 tests
b- Ask the contractor to submit a change request to the Change Control Board (CCB)
c- Look at the penalty clauses in the contract to see if the sponsor can reduce your fee
d- Ask the sponsor if it is ok to reduce the number of tests
2- our instructor has a patio construction project ongoing. The project has the following earned value management data: Present Value (PV) = $48,000, Earned Value (EV) = 32,000, and Actual Costs = $44,000. What is the Cost Variance (CV) for the project?

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 10:00, lm942747
What is the difference between an "i" statement and a "you" statement? a. the "i" statement is non-confrontational b. the "you" statement is non-confrontational c. the "i" statement is argumentative d. the "you" statement is neutral in tone select the best answer from the choices provided
Answers: 1
image
Business, 22.06.2019 13:30, brittanysanders
1. is the act of declaring a drivers license void and terminated when it is determined that the license was issued through error or fraud.
Answers: 2
image
Business, 22.06.2019 17:20, shakira11harvey6
Andy owns islander surfboard inc. in the past, andy has always given his employees bonuses during the holidays if they reached certain sales goals. this year, even though the company is thriving, he decided to cut bonuses from employees and award them to himself instead. what ethical theory of leadership is andy following?
Answers: 1
image
Business, 22.06.2019 19:10, jaylene125
Robin hood has hired you as his new strategic consultant to him successfully transform his social change enterprise. robin has told you that he counting on your strategic management knowledge to him and his merrymen achieve their goals. discuss in detail what you think should be robin’s two primary strategic goals and continue by also explaining your analytical reasons that support your recommendations.
Answers: 3
You know the right answer?
1- You are the Project Manager of a large project. One of your contractors sends you an email reques...

Questions in other subjects:

Konu
Mathematics, 25.11.2021 14:10