g Your project is tasked with the excavation of 1,000,000 cubic feet of soil. According to the project management plan you need to excavate 60,000 cubic feet of soil per week at a cost of $5 per cubic feet. According to the first month’s progress report, the project’s EV was 1,000,000 and the AC was 1,200,000. According to the second month’s progress report, the project’s EV was 2,200,000 and the AC was 4,400,000. After the 3rd month (12 weeks) you have 250,000 cubic feet of soil remaining to be excavated and your total cost to date is 4,000,000. What is the schedule performance index?

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 10:00, bob7220
Your father offers you a choice of $120,000 in 11 years or $48,500 today. use appendix b as an approximate answer, but calculate your final answer using the formula and financial calculator methods. a-1. if money is discounted at 11 percent, what is the present value of the $120,000?
Answers: 3
image
Business, 22.06.2019 20:00, zay12350
Which motion below could be made so that the chair would be called on to enforce a violated rule?
Answers: 2
image
Business, 22.06.2019 20:00, tvoalicea
Harry is 25 years old with a 1.55 rating factor for his auto insurance. if his annual base premium is $1,012, what is his total premium? $1,568.60 $2,530 $1,582.55 $1,842.25
Answers: 1
image
Business, 22.06.2019 20:10, Maria3737
Quick computing currently sells 12 million computer chips each year at a price of $19 per chip. it is about to introduce a new chip, and it forecasts annual sales of 22 million of these improved chips at a price of $24 each. however, demand for the old chip will decrease, and sales of the old chip are expected to fall to 6 million per year. the old chips cost $10 each to manufacture, and the new ones will cost $14 each. what is the proper cash flow to use to evaluate the present value of the introduction of the new chip? (enter your answer in millions.)
Answers: 1
You know the right answer?
g Your project is tasked with the excavation of 1,000,000 cubic feet of soil. According to the proje...