A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will the project leader decide which activity should be scheduled first? a. The activity with the most slack
b. The activity with the least slack
c. The activity with the smallest duration
d. The activity with the lowest identification number
e. The activity with the highest cost

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 05:00, MaxxL
One question from a survey was "how many credit cards do you currently have? " the results of the survey are provided. complete parts (a) through (g) below. click the icon to view the survey results. (a) determine the mean number of credit cards based on the raw data. the mean is 3.113.11 credit cards. (type an integer or a decimal. do not round.) (b) determine the standard deviation number of credit cards based on the raw data. the standard deviation is 1.9111.911 credit cards. (round to three decimal places as needed.) (c) determine a probability distribution for the random variable, x, the number of credit cards issued to an individual. x (# of cards) p(x) x (# of cards) p(x) 1 0.280.28 6 nothing 2 nothing 7 nothing 3 nothing 8 nothing 4 nothing 9 nothing 5 nothing 10 nothing (type integers or decimals. do not round.)
Answers: 2
image
Business, 22.06.2019 20:30, boog89
Mordica company identifies three activities in its manufacturing process: machine setups, machining, and inspections. estimated annual overhead cost for each activity is $156,960, $382,800, and $84,640, respectively. the cost driver for each activity and the expected annual usage are number of setups 2,180, machine hours 25,520, and number of inspections 1,840. compute the overhead rate for each activity. machine setups $ per setup machining $ per machine hour inspections $ per inspection
Answers: 1
image
Business, 23.06.2019 00:30, danny123421
It's possible for a debt card transaction to bounce true or false
Answers: 1
image
Business, 23.06.2019 02:20, maustin5323
Which one of the following is not a typical current liability? a. interest payable b. current maturities of long-term debt c. salaries payable d. mortgages payable
Answers: 3
You know the right answer?
A project leader has realized that two activities in the project cannot be done at the same time bec...

Questions in other subjects:

Konu
Mathematics, 05.05.2021 23:00
Konu
Biology, 05.05.2021 23:00
Konu
Physics, 05.05.2021 23:00