When budgeting for personnel, hospitals typically use FTEs to calculate the number of employee hours needed to process the work tasks in a given department, unit, or function. FTEs (full-time equivalent) are generally calculated on the typical workweek as defined by the facility: •1 FTE = 40 hours/week •40 hours/week x 52 weeks = 2,080 hours/year
The second part of the staffing calculation consists of estimating the volume of work to be done. •Work standard: 16 minutes to draw blood from a patient
•Volume per day: 60 patients needing blood drawn
•60 patients x 16 minutes = 960 minutes needed each day
•1 FTE = 480 minutes per work day
•960 / 480 = 2.0
Needed: 2.0 FTEs to process 60 patients per day

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 17:30, lanamiami
After the embarrassing sign incident at the restaurant you own, you decide to offer employees a six-week fundamental writing skills workshop. a local business communication instructor, who has experience teaching writing skills at treleaven community college, will facilitate the sessions. to encourage employees to attend these optional sessions, write an email that explains why you’re offering the workshop and why employees should participate.
Answers: 2
image
Business, 22.06.2019 20:00, adriannacomrosenbark
Modern firms increasingly rely on other firms to supply goods and services instead of doing these tasks themselves. this increased level of is leading to increased emphasis on management.
Answers: 2
image
Business, 22.06.2019 20:30, lareynademividp0a99r
The smelting department of kiner company has the following production and cost data for november. production: beginning work in process 3,700 units that are 100% complete as to materials and 23% complete as to conversion costs; units transferred out 10,500 units; and ending work in process 8,100 units that are 100% complete as to materials and 41% complete as to conversion costs. compute the equivalent units of production for (a) materials and (b) conversion costs for the month of november.
Answers: 3
image
Business, 22.06.2019 20:30, boog89
Mordica company identifies three activities in its manufacturing process: machine setups, machining, and inspections. estimated annual overhead cost for each activity is $156,960, $382,800, and $84,640, respectively. the cost driver for each activity and the expected annual usage are number of setups 2,180, machine hours 25,520, and number of inspections 1,840. compute the overhead rate for each activity. machine setups $ per setup machining $ per machine hour inspections $ per inspection
Answers: 1
You know the right answer?
When budgeting for personnel, hospitals typically use FTEs to calculate the number of employee hours...

Questions in other subjects: