For an activity in a CPM analysis the Early Start time is 15 and the Late Start time is 20. Which of the following statements is true? a. The duration of this task is zero.
b. The slack for this activity is 20.
c. The activity's late start must happen before its early start.
d. The activity is not on the critical path.
e. The duration of this task is 20.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 00:20, randallmatthew6124
Suppose an economy consists of three sectors: energy (e), manufacturing (m), and agriculture (a). sector e sells 70% of its output to m and 30% to a. sector m sells 30% of its output to e, 50% to a, and retains the rest. sector a sells 15% of its output to e, 30% to m, and retains the rest.
Answers: 1
image
Business, 22.06.2019 02:30, damiangibson2
Question 1 which of the following tasks use your roommate as a resource? choose all answers which apply. take order wash the mixer’s bowl and mix the dough spoon cookies onto the tray unload the cookies from the oven pack the cookies 1 points question 2 which of the following tasks use the tray(s) as a resource? choose all answers which apply. take order wash the mixer’s bowl and mix the dough bake the cookies cool the cookies accept payment 1 points question 3 determine the task time for the following tasks. fill integer numbers into the blank (e. g., 5 rather than 5.0) wash and mixing the dough: minute(s)/order spoon cookies onto the tray: minute(s)/order set up timer: minute(s)/order bake: minute(s)/order cool the cookies: minute(s)/order pack the cookies: minute(s)/order accept payment: minute(s)/order 2 points question 4 q4: determine the cycle time for the following resources. fill integer numbers into the blank (e. g., 5 rather than 5.0) kristen (you): minute(s) roommate: minute(s) oven: minute(s) 2 points question 5 what is the capacity rate (in orders/hour) of the roommate? 1 points question 6 what is the capacity rate (in orders/hour) of the whole process? 2 points question 7 how long (in minutes) it takes to process the first order?
Answers: 3
image
Business, 22.06.2019 11:20, johnlecona210
Security a has a higher standard deviation of returns than security b. we would expect that: (i) security a would have a risk premium equal to security b. (ii) the likely range of returns for security a in any given year would be higher than the likely range of returns for security b. (iii) the sharpe ratio of a will be higher than the sharpe ratio of b. (a) i only (b) i and ii only (c) ii and iii only (d) i, ii and iii
Answers: 1
image
Business, 22.06.2019 19:00, leeenaaa95
What is an equation of the line in slope intercept formm = 4 and the y-intercept is (0,5)y = 4x-5y = -5x +4y = 4x + 5y = 5x +4
Answers: 1
You know the right answer?
For an activity in a CPM analysis the Early Start time is 15 and the Late Start time is 20. Which of...

Questions in other subjects: