The following set of 4 jobs is to be processed through 2 work centers. The sequence is first printing, then binding. Processing time at each of the work centers is shown in the following table. Job Printing (hours) Binding (hours)
U 17 5
V 9 11
W 6 12
X 9 8
What is the total time to complete these 4 jobs through both work centers if Johnson's Sequence is employed?
a. 46.
b. 45.
c. 44.
d. 47.

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 13:30, drippyc334
What do you recommend adam do to increase production in a business setting that does not seem to value high productivity?
Answers: 3
image
Business, 22.06.2019 17:20, spycn5069
Arecession is defined as a period in which
Answers: 1
image
Business, 22.06.2019 17:30, chilanka
Dr. sperry, a biologist, is using excel to track growth rates of different populations of bacteria. she has a very complex formula in one cell. it begins with “round”. dr. sperry would like to see exactly how excel’s calculation reached the final rounded value that she sees in the cell. what could dr. sperry do to best understand how the calculation was made? try different formulas on her own until she reaches the value shown in excel click on the evaluate formula button in the formulas tab and then click “step in” select the cell and then look at the formula in the formula field of the ribbon remove “round” from the formula in order to see the actual value before rounding
Answers: 2
image
Business, 22.06.2019 20:50, ineedhelpireallydo
Power plants that rely on coal increase the amount of sulfur dioxide that dissolves into the air, eventually increasing the acidity of precipitation. the higher acidity of rain and snow can damage forests by making it more difficult for plants to absorb minerals from the soil. the equations below provide information about the market demand and supply of electricity. there is a constant marginal external cost of $25 per unit of electricity. d: qd= 200 – 2ps: qs=p – 10what quantity of electricity satisfies allocative efficiency in this market? a. 60b. 70c. 50d. 43.3
Answers: 2
You know the right answer?
The following set of 4 jobs is to be processed through 2 work centers. The sequence is first printin...

Questions in other subjects: