The Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safety regulations. The OSHA inspectors ordered the mill to alter some existing machinery to make it safer (add safety guards, etc.); purchase some new machinery to replace older, dangerous machinery; and relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gave the mill only 35 weeks to make the changes; if the changes were not made by then, the mill would be fined $300,000. The mill determined the activities in a CPM/PERT network that would have to be completed and then estimated the indicated activity times, as shown in the following table: Time Estimates (weeks)
Activity Activity Description Activity Predecessor a m b
a Order new machinery — 1 2 3
b Plan new physical layout — 2 5 8
c Determine safety changes in existing machinery — 1 3 5
d Receive equipment a 4 10 25
e Hire new employees a 3 7 12
f Make plant alterations b 10 15 25
g Make changes in existing machinery c 5 9 14
h Train new employees d, e 2 3 7
i Install new machinery d, e, f 1 4 6
j Relocate old machinery d, e, f, g 2 5 10
k Conduct employee safety orientation h, i, j 2 2 2
Construct the project network for this project and determine the following:
a. Expected activity times
b. Earliest and latest activity times and activity slack
c. Critical path
d. Expected project duration and variance
e. The probability that the mill will be fined $300,000

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 16:30, hvbrown28
What are some of the miranda restrictions on questioning someone?
Answers: 1
image
Business, 22.06.2019 00:00, famouzgal
Ok, so, theoretical question: if i bought the mona lisa legally, would anyone be able to stop me from eating it? why or why not?
Answers: 1
image
Business, 22.06.2019 12:20, Tierriny576
If jobs have been undercosted due to underallocation of manufacturing overhead, then cost of goods sold (cogs) is too low and which of the following corrections must be made? a. decrease cogs for double the amount of the underallocation b. increase cogs for double the amount of the underallocation c. decrease cogs for the amount of the underallocation d. increase cogs for the amount of the underallocation
Answers: 3
image
Business, 22.06.2019 18:00, 20jhuffman
Bond j has a coupon rate of 6 percent and bond k has a coupon rate of 12 percent. both bonds have 14 years to maturity, make semiannual payments, and have a ytm of 9 percent. a. if interest rates suddenly rise by 2 percent, what is the percentage price change of these bonds?
Answers: 2
You know the right answer?
The Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safet...

Questions in other subjects:

Konu
Mathematics, 11.03.2020 03:01