Business, 14.05.2021 01:40 bossefamily1

A company has 29,600 machine hours available for producing A and B. Consider the following information: Product A Product B
Required machine time per unit (hours) 3 4
Maximum demand (units) 5,000 6,000
Contribution margin per unit $5 $6
Contribution margin per labor hour $2.00 $1.50

If the company follows proper managerial accounting practices, what production schedules should the company set?

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 19:20, justintisdale95
Which of the following areas provides residents with close access to high-paying jobs and cultural attractions? a. the suburbs b. exurbs c. rural areas d. the city 2b2t
Answers: 3
image
Business, 21.06.2019 22:50, DnakMeme6e7272727272
The leading producer of cell phone backup batteries, jumpstart, has achieved great success because they produce high-quality battery backups that are not too expensive. even so, another company that produces lower-quality batteries at the same price has also achieved some success, but not as much as jumpstart. also, in general, the price of backup batteries has declined because of economies of scale and learning. in addition, jumpstart has added complementary assets, such as a carrying case. considering all of these factors, the backup battery industry is most likely in the introduction stage. growth stage. shakeout stage. maturity stage.
Answers: 2
image
Business, 22.06.2019 02:30, kseniyayakimno
Luc do purchased stocks for $6,000. he paid $4,000 in cash and borrowed $2,000 from the brokerage firm. he bought 100 shares at $60.00 per share ($6,000 total). the loan has an annual interest rate of 8 percent. six months later, luc do sold the stock for $65 per share. he paid a commission of $120 and repaid the loan. his net profit was how much? pls
Answers: 3
image
Business, 22.06.2019 19:40, cieloromero1
Moody corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. at the beginning of the year, the company made the following estimates: machine-hours required to support estimated production 100,000 fixed manufacturing overhead cost $ 650,000 variable manufacturing overhead cost per machine-hour $ 3.00 required: 1. compute the plantwide predetermined overhead rate. 2. during the year, job 400 was started and completed. the following information was available with respect to this job: direct materials $ 450 direct labor cost $ 210 machine-hours used 40
Answers: 3
You know the right answer?
A company has 29,600 machine hours available for producing A and B. Consider the following informati...

Questions in other subjects:

Konu
Biology, 10.05.2020 19:57