Calculating the Variable Overhead Spending and Efficiency Variances Standish Company manufactures consumer products and provided the following information for the month of February: Units produced 131,000
Standard direct labor hours per unit 0.20
Standard variable overhead rate (per direct labor hour) $3.40
Actual variable overhead costs $88,670
Actual hours worked 26,350
Required:
1. Calculate the total variable overhead variance.
2. What if actual production had been 129,500 units?

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 14:30, jraemier5861
Island novelties, inc., of palau makes two products—hawaiian fantasy and tahitian joy. each product's selling price, variable expense per unit and annual sales volume are as follows:
Answers: 2
image
Business, 22.06.2019 04:30, mt137896
Required prepare the necessary adjusting entries in the general journal as of december 31, assuming the following: on september 1, the company entered into a prepaid equipment maintenance contract. birch company paid $3,400 to cover maintenance service for six months, beginning september 1. the payment was debited to prepaid maintenance. supplies on hand at december 31 are $3,900. unearned commission fees at december 31 are $7,000. commission fees earned but not yet billed at december 31 are $3,500. (note: debit fees receivable.) birch company's lease calls for rent of $1,600 per month payable on the first of each month, plus an annual amount equal to 1% of annual commissions earned. this additional rent is payable on january 10 of the following year. (note: be sure to use the adjusted amount of commissions earned in computing the additional rent.)
Answers: 1
image
Business, 22.06.2019 16:50, mariposa91
In terms of the "great wheel of science", statistics are central to the research process (a) only between the hypothesis phase and the observation phase (b) only between the observation phase and the empirical generalization phase (c) only between the theory phase and the hypothesis phase (d) only between the empirical generalization phase and the theory phase
Answers: 1
image
Business, 22.06.2019 20:40, AliTop232
The largest elements of community corrections are
Answers: 1
You know the right answer?
Calculating the Variable Overhead Spending and Efficiency Variances Standish Company manufactures co...

Questions in other subjects:

Konu
Mathematics, 05.02.2020 12:46