An activity on the critical path of a project was scheduled to be completed within 12 weeks, with a budget of $8,000. During a performance review, which took place 7 weeks after the activity was initiated, it was found that 50% of the work had already been completed and that the actual cost was $4,500. Calculate the EV of the activity. Calculate the CI and SI for the activity. Calculate the expected BAC using the original estimate approach. Calculate the expected BAC using the revised estimate approach. Compare and discuss the results obtained in parts (c) and (d).

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 21:20, jesus3426
According to the u. s. census bureau (), the median household income in the united states was $23,618 in 1985, $34,076 in 1995, $46,326 in 2005, and $57,230 in 2015. in purchasing power terms, how did family income compare in each of those four years? you will need to know that the cpi (multiplied by 100, 1982–1984 = 100) was 107.6 in 1985, 152.4 in 1995, 195.3 in 2005, and 237.0 in 2015
Answers: 3
image
Business, 22.06.2019 11:00, aiueo946
Aprofessional does specialized work that's primarily: degree based. medical or legal. well paying. intellectual and creative
Answers: 2
image
Business, 22.06.2019 20:20, abbz13
Which statement is not true about a peptide bond? which statement is not true about a peptide bond? the peptide bond has partial double-bond character. the carbonyl oxygen and the amide hydrogen are most often in a trans configuration with respect to one another. rotation is restricted about the peptide bond. the peptide bond is longer than the typical carbon-nitrogen bond.
Answers: 2
image
Business, 23.06.2019 04:40, maguilarz2005
2. a computer equipment was acquired at the beginning of the year at a cost of $56,000 with an estimated residual value of $5,000, and an estimated useful life of five years. determine the second year’s depreciation expense using the straight-line method.
Answers: 3
You know the right answer?
An activity on the critical path of a project was scheduled to be completed within 12 weeks, with a...

Questions in other subjects:

Konu
Mathematics, 21.12.2020 03:30
Konu
Mathematics, 21.12.2020 03:30
Konu
Mathematics, 21.12.2020 03:30