At​ Symtecks, the output of a process is valued at ​$ per unit. The cost of labor is ​$ per hour including benefits. The accounting department provided the following information about the process for the past four​ weeks: Week 1 Week 2 Week 3 Week 4
Units Produced 1124 1,310 1,092 981
Labor (S) 12,735 14,842 10,063 9,526
Material (S) 21,041 24,523 20,442 18,364
Overhead (S) 8,992 10,480 8,736 7,848

Required:
a. Use the multifactor productivity ratio to see whether recent process improvements had any effect and, if so, when the effect was noticeable.
b. Has labor productivity changed? use the labor productivity ratio to support your answer.

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 04:00, 702580
Medtronic, inc., is a medical technology company that competes for customers with st. jude medical s. c., inc. james hughes worked for medtronic as a sales manager. his contract prohibited him from working for a competitor for one year after leaving medtronic. hughes sought a position as a sales director for st. jude. st. jude told hughes that his contract with medtronic was unenforceable and offered him a job. hughes accepted. medtronic filed a suit, alleging wrongful interference. which type of interference was most likely the basis for this suit? did it occur here? medtronic, inc., is a medical technology company that competes for customers with st. jude medical s. c., inc. james hughes worked for medtronic as a sales manager. his contract prohibited him from working for a competitor for one year after leaving medtronic
Answers: 2
image
Business, 22.06.2019 16:40, kat1191
Job applications give employers uniform information for all employees, making it easier to
Answers: 1
image
Business, 22.06.2019 20:40, Jacobstoltzfus
Review the wbs and gantt chart you created previously. propose three to five additional activities that would you estimate resources and durations. now, identify at least eight milestones for the recreation and wellness intranet project. remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone. add your activities and milestones to your gantt chart, creating a new gantt chart. estimate the task durations and enter dependencies as appropriate. remember that your schedule goal for the project is six months. copy the gantt chart and network diagram to a word document.
Answers: 2
image
Business, 23.06.2019 01:10, aris35
Hillside issues $4,000,000 of 6%, 15-year bonds dated january 1, 2016, that pay interest semiannually on june 30 and december 31. the bonds are issued at a price of $4,895,980. required: 1. prepare the january 1, 2016, journal entry to record the bonds’ issuance
Answers: 3
You know the right answer?
At​ Symtecks, the output of a process is valued at ​$ per unit. The cost of labor is ​$ per hour inc...

Questions in other subjects:

Konu
History, 23.09.2020 01:01