Lewis Noodles has the following cooking procedures. You will need to compute the TAKT time per day and the minimum number of workstations assuming eight working hours a day and 80 units need to be made per day. Task Description Task Time Preceding Task
A cook vegetables 2 minutes
B Cut noodles 1 minute A
C Cook noodles 5 minutes B
D Cook meat 3 minutes C
E Mix ingredients 1 minute D

a. TAKT-time= minutes
b. Theoretical Minimum # of Station =
c. Efficiency (%)

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 03:10, hipstergirl225
Beswick company your team is allocated a project involving a major client, the beswick company. although the organization has many clients, this client, and project, is the largest source of revenue and affects the work of several other teams in the organization. the project requires continuous involvement with the client, so any problems with the client are immediately felt by others in the organization. jamie, a member of your team, is the only person in the company with whom this client is willing to deal. it can be said that jamie has:
Answers: 2
image
Business, 22.06.2019 14:40, nathenq1839
Which of the following would classify as a general education requirement
Answers: 1
image
Business, 22.06.2019 17:20, andrespeerman
States that if there is no specific employment contract saying otherwise, the employer or employee may end an employment relationship at any time, regardless of cause. rule of fair treatment due-process policy rule of law employment flexibility employment at will
Answers: 1
image
Business, 22.06.2019 21:30, lekylawhite16
Abond purchased for $950 was sold for $980 after one year. the interest received during the year is $25. the bond's yield is:
Answers: 1
You know the right answer?
Lewis Noodles has the following cooking procedures. You will need to compute the TAKT time per day a...

Questions in other subjects:

Konu
English, 19.11.2020 19:10