Project C: What is the total crash cost for crashing the following project by FOUR days? Activity Immediate Normal Time Crash Time Normal Cost Crash Cost CC in $ 8000 7000 Predecessor NT in days CT in days NC in 7000 5000 9000 | A. D B, C 5000 3000 2000 4000 5000 E, F 7000 a. $4000 b. $1500 c. $3000 d. $2500

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 21:30, anonymous1813
Balance sheet baggett company's balance sheet accounts and amounts as of december 31, 2016, are shown in random order as follows: account debit (credit) account debit (credit) income taxes payable $(3,800) additional paid-in capital on preferred prepaid items 1,800 stock $(7,900) additional paid-in capital on common stock (9,300) allowance for doubtful accounts (1,600) land 12,200 bonds payable (due 2020) (23,000) notes payable (due 2019) (6,000) buildings 57,400 notes receivable (due 2018) 16,400 sinking fund to retire bonds payable 5,000 accounts receivable 12,600 advances from customers (long-term) (2,600) premium on bonds payable (1,400) cash 4,300 accounts payable (13,100) accumulated depreciation: equipment (9,700) inventory 7,400 retained earnings (18,300) accumulated depreciation: buildings (21,000) preferred stock, $100 par (18,600) patents (net) 4,600 wages payable (1,400) equipment 28,700 common stock, $10 par (12,700) required: 1. prepare a december 31, 2016 balance sheet for the baggett. baggett company balance sheet december 31, 2016 assets current assets: $ $ $ long-term investments: $ property, plant, and equipment: $ $ $ intangible assets: liabilities current liabilities: $ $ long-term liabilities: $ $ other liabilities: shareholders' equity contributed capital: $ $ $ $ 2. compute the debt-to-assets ratio. round to one decimal place. do not enter a percent sign (%) as part of your answer. %
Answers: 1
image
Business, 22.06.2019 02:30, kkpsmith
Required information [the following information applies to the questions displayed below.] the following data is provided for garcon company and pepper company. garcon company pepper company beginning finished goods inventory $ 13,800 $ 18,850 beginning work in process inventory 16,700 20,700 beginning raw materials inventory 8,800 13,500 rental cost on factory equipment 28,250 26,650 direct labor 22,400 37,400 ending finished goods inventory 17,300 14,300 ending work in process inventory 23,200 19,400 ending raw materials inventory 5,900 9,600 factory utilities 11,250 15,000 factory supplies used 10,900 5,700 general and administrative expenses 32,500 44,500 indirect labor 2,500 9,880 repairs—factory equipment 4,820 2,150 raw materials purchases 41,500 63,000 selling expenses 54,800 49,000 sales 238,530 317,510 cash 33,000 23,700 factory equipment, net 222,500 124,825 accounts receivable, net 13,400 23,950 required: 1. complete the table to find the cost of goods manufactured for both garcon company and pepper company for the year ended december 31, 2017. 2. complete the table to calculate the cost of goods sold for both garcon company and pepper company for the year ended december 31, 2017.
Answers: 2
image
Business, 22.06.2019 12:50, sunshine0613
Explain whether each of the following events increases or decreases the money supply. a. the fed buys bonds in open-market operations. b. the fed reduces the reserve requirement. c. the fed increases the interest rate it pays on reserves. d. citibank repays a loan it had previously taken from the fed. e. after a rash of pickpocketing, people decide to hold less currency. f. fearful of bank runs, bankers decide to hold more excess reserves. g. the fomc increases its target for the federal funds rate.
Answers: 3
image
Business, 22.06.2019 17:50, ratpizza
Abc factory produces 24,000 units. the cost sheet gives the following information: direct materials rs. 1,20,000direct labour rs. 84,000variable overheads rs. 48,000semi variable overheads rs. 28,000fixed overheads rs. 80,000total cost rs. 3,60,000presently the product is sold at rs. 20 per unit. the management proposes to increase the production by 3,000 units for sales in the foreign market . it is estimated that semi variable overheads will increase by rs. 1,000. but the product will be sold at rs. 14 per unit in the foreign market. however, no additional capital expenditure will be incurredq-1. what is present profit of the company ? q-2. what is proposed profit of the company in new market? q-3.what is suggestion for new makret proposal whether proposal accept or not
Answers: 1
You know the right answer?
Project C: What is the total crash cost for crashing the following project by FOUR days? Activity Im...

Questions in other subjects:

Konu
Mathematics, 15.04.2021 22:40