A project begins in January 2014; it is to be completed in October 2016. The contract price is $3,900 and the estimated total cost of the project is $3,000. Additional data for the project is provided below:
2014 2015 2016
Costs Incurred To Date $300 $2,400 $4,200
Estimated cost to Complete 2,700 1,600
Estimated Total Cost $3,000 $4,000 $4,200
Percentage of completion [PC]= (Costs incurred to date)/(Estimated total cost)
Required:
Compute the gross profit/loss recognized for each year under the PC method.
Answers: 1
Business, 22.06.2019 03:20, emilyplays474
Look at this check register. calculate the current balance. check date transaction (+) deposit balance 5/1 5/3 $82.92 debit 8.00 78.24 005 monthly fee phone bill paycheck 1 125.00 5/15 5/17 5/20 atm 40.00 56.50 006 t ennis lessons the current balance is?
Answers: 1
Business, 23.06.2019 00:00, zhellyyyyy
The gorman group is a financial planning services firm owned and operated by nicole gorman. as of october 31, 2016, the end of the fiscal year, the accountant for the gorman group prepared an end-of-period spreadsheet, part of which follows:
Answers: 2
A project begins in January 2014; it is to be completed in October 2016. The contract price is $3,90...
Biology, 14.05.2021 02:00
Arts, 14.05.2021 02:00
English, 14.05.2021 02:00
Mathematics, 14.05.2021 02:00