The cost slope of an activity $ 250/day. The normal duration of this activity is 15 days, the crash cost is $1,500 and the maximum crashing possible for the activity is 10 days beyond the normal duration. What is the normal cost of this activity

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 11:00, jilliand2030
Why are the four primary service outputs of spatial convenience, lot size, waiting time, and product variety important to logistics management? provide examples of competing firms that differ in the level of each service output provided to customers?
Answers: 1
image
Business, 22.06.2019 13:00, dondre54
Explain the relationship between consumers and producers in economic growth and activity
Answers: 1
image
Business, 23.06.2019 01:10, KariSupreme
Atariff on avocadoes the price of avocadoes, consumers' surplus for avocado buyers, producers' surplus of avocado growers and tariff revenue. because the loss to is more than the gain to there is a net loss to society. raises; decreases; increases; generates; consumers; producers and government raises; increases; decreases; does not generate; producers and government; consumers lowers; increases; decreases; does not generate; producers and government; consumers raises; increases; decreases; generates; producers; consumers and government
Answers: 2
image
Business, 23.06.2019 22:40, ramandeep
How did the study organizers fix the game of monopoly to ensure certain players win?
Answers: 2
You know the right answer?
The cost slope of an activity $ 250/day. The normal duration of this activity is 15 days, the crash...

Questions in other subjects:

Konu
Social Studies, 05.12.2019 10:31
Konu
Biology, 05.12.2019 10:31
Konu
Chemistry, 05.12.2019 10:31