Task C has two immediate predecessors, Tasks A and B. Task C also has two immediate followers, Tasks D and E. Task A has an early finish time of 3 days, and Task B has an early finish time of 5 days. Task D has a late start time of 10 days and Task E has a late start time of 8 days. Task C is 2 days long. What is the early start time of Task C? A. 7 days
B. 5 days
C. 8 days
D. 2 days
E. 6 days

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 19:20, sam10146
Chester has a credit score of 595 according to the following table his credit rating is considered to be which of these
Answers: 1
image
Business, 23.06.2019 01:00, jerzie53
Gideon company uses the allowance method of accounting for uncollectible accounts. on may 3, the gideon company wrote off the $2,000 uncollectible account of its customer, a. hopkins. on july 10, gideon received a check for the full amount of $2,000 from hopkins. on july 10, the entry or entries gideon makes to record the recovery of the bad debt is
Answers: 1
image
Business, 23.06.2019 02:00, jackfrost5
How much more output does the $18 trillion u. s. economy produce when gdp increases by 3.0 percen?
Answers: 1
image
Business, 23.06.2019 06:30, samlolomg123
What did surprise you in personalities
Answers: 1
You know the right answer?
Task C has two immediate predecessors, Tasks A and B. Task C also has two immediate followers, Tasks...

Questions in other subjects:

Konu
Mathematics, 21.09.2019 19:00