Business, 16.12.2020 16:30 bob7220

A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 19:30, aquinomoises518
Maker-bot corporation has 10,000 shares of 10%, $90 par value, cumulative preferred stock outstanding since its inception. no dividends were declared in the first two years. if the company pays $400,000 of dividends in the third year, how much will common stockholders receive?
Answers: 2
image
Business, 22.06.2019 10:00, emwemily
Frolic corporation has budgeted sales and production over the next quarter as follows. the company has 4100 units of product on hand at july 1. 10% of the next months sales in units should be on hand at the end of each month. october sales are expected to be 72000 units. budgeted sales for september would be: july august september sales in units 41,500 53,500 ? production in units 45,700 53,800 58,150
Answers: 3
image
Business, 22.06.2019 16:30, allytrujillo20oy0dib
Summarize the specific methods used by interest groups in order to influence governmental decisions making in all three branches of government. provide at least two examples from each branch.
Answers: 3
image
Business, 22.06.2019 19:50, crzyemo865
Aproduction line has three machines a, b, and c, with reliabilities of .96, .86, and .85, respectively. the machines are arranged so that if one breaks down, the others must shut down. engineers are weighing two alternative designs for increasing the line’s reliability. plan 1 involves adding an identical backup line, and plan 2 involves providing a backup for each machine. in either case, three machines (a, b, and c) would be used with reliabilities equal to the original three. a. compute overall system reliability under plan 1. (round your intermediate calculations and final answer to 4 decimal places.) reliability b. compute overall system reliability under plan 2. (round your intermediate calculations and final answer to 4 decimal places.) reliability c. which plan will provide the higher reliability? plan2plan1
Answers: 3
You know the right answer?
A project activity has an earliest completion time of 5, an activity time of 3, and a latest complet...

Questions in other subjects:

Konu
Mathematics, 14.12.2020 22:00
Konu
Mathematics, 14.12.2020 22:00