subject
Business, 20.10.2020 18:01 laurieburgess804

If the budget at completion for a project is $200,000 and the cost performance index is .5, what is the estimate at completion

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 10:30, Uc34758
Issued to the joint planning and execution community (jpec) initiates the development of coas; it also requests that the supported ccdr submit a commander's estimate of the situation with a recommended coa to resolve the situation (joint force command and staff participation in the joint operation planning and execution system, page 10)
Answers: 2
image
Business, 22.06.2019 11:00, saurav76
When using various forms of promotion to carry the promotion message, it is important that the recipients of the message interpret it in the same way. creating a unified promotional message, where potential customers perceive the same message, whether it is in a tv commercial, or on a billboard, or in a blog, is called
Answers: 2
image
Business, 22.06.2019 11:20, smn43713
Which stage of group development involves members introducing themselves to each other?
Answers: 3
image
Business, 22.06.2019 16:10, ilovemusicandreading
The brs corporation makes collections on sales according to the following schedule: 30% in month of sale 66% in month following sale 4% in second month following sale the following sales have been budgeted: sales april $ 130,000 may $ 150,000 june $ 140,000 budgeted cash collections in june would be:
Answers: 1
You know the right answer?
If the budget at completion for a project is $200,000 and the cost performance index is .5, what is...