Sutter Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 10,000
Total fixed manufacturing overhead cost $35,000
Variable manufacturing overhead per machine-hour $2.20

Recently, Job T369 was completed with the following characteristics:

Number of units in the job 10
Total machine-hours 40
Direct materials $750
Direct labor cost $1,560

If the company marks up its unit product costs by 20% then the selling price for a unit in Job T369 is closest to:

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 06:00, aliami0306oyaj0n
Use this image to answer the following question. when the economy is operating at point b, the us congress is most likely to follow
Answers: 3
image
Business, 23.06.2019 06:00, lover23707
Before setting your prices, it's wise to a. subtract your profit margin from your costs. b. research industry standards. c. memorize the formula for cost plus. d. ignore your competitors' prices.
Answers: 1
image
Business, 23.06.2019 19:30, sergiog6833
You are offered a free ticket to see the chicago cubs play the chicago white sox at wrigley field. assume the ticket has no resale value. willie nelson is performing on the same night, and his concert is your next-best alternative activity. tickets to see willie nelson cost $40. on any given day, you would be willing to pay up to $50 to see and hear willie nelson perform. assume there are no other costs of seeing either event. based on this information, at a minimum, how much would you have to value seeing the cubs play the white sox to accept the ticket and go to the game? a. $0b. $40c. $10d. $50
Answers: 1
image
Business, 24.06.2019 04:00, yolo123321
How do unseen costs make it difficult to decide if it is better for government or private companies/people to spend our money? provide an example using a “seen” and “unseen” cost to prove your answer.
Answers: 3
You know the right answer?
Sutter Corporation uses a job-order costing system with a single plantwide predetermined overhead ra...

Questions in other subjects: