The management of Griswell Corporation would like to investigate the possibility of basing its predetermined overhead rate on activity at capacity. The company's controller has provided an example to illustrate how this new system would work. In this example, the allocation base is machine-hours and the estimated amount of the allocation base for the upcoming year is 39,000 machine-hours. In addition, capacity is 45,000 machine-hours and the actual level of activity for the year is 40,200 machine-hours. All of the manufacturing overhead is fixed and is $702,000 per year. For simplicity, it is assumed that this is the estimated manufacturing overhead for the year as well as the manufacturing overhead at capacity. It is further assumed that this is also the actual amount of manufacturing overhead for the year. If the company bases its predetermined overhead rate on capacity, by how much was manufacturing overhead underapplied or overapplied? a) $262,191 Overappliedb) $76,797 Underappliedc) $76,797 Overapplied
d) $262,191 Underapplied

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 21:30, mbol7123
Asavings account that pays interest every 3 months is said to have a interest period
Answers: 1
image
Business, 22.06.2019 12:50, tayjohn9774
Kendrick is leaving his current position at a company, and charlize is taking over. kendrick set up his powerpoint for easy access for himself. charlize needs to work in the program that is easy for her to use. charlize should reset advanced options
Answers: 3
image
Business, 22.06.2019 17:10, suxy16
Calculate riverside’s financial ratios for 2014. assume that riverside had $1,000,000 in lease payments and $1,400,000 in debt principal repayments in 2014. (hint: use the book discussion to identify the applicable ratios.)
Answers: 3
image
Business, 22.06.2019 19:20, dayday0
Six years ago, an 80-kw diesel electric set cost $160,000. the cost index for this class of equipment six years ago was 187 and is now 194. the cost-capacity factor is 0.6. the plant engineering staff is considering a 120-kw unit of the same general design to power a small isolated plant. assume we want to add a precompressor, which (when isolated and estimated separately) currently costs $13291. determine the total cost of the 120-kw unit. (hint: skip $ and comma symbols)
Answers: 3
You know the right answer?
The management of Griswell Corporation would like to investigate the possibility of basing its prede...

Questions in other subjects:

Konu
Mathematics, 11.10.2020 14:01
Konu
Mathematics, 11.10.2020 14:01