Direct manufacturing labor and direct materials variances, missing data. (CMA, heavily adapted) Oyster Bay Surfboards manufactures fiberglass surfboards. The standard cost of direct materials and direct manufacturing labor is $248 per board. This includes 35 pounds of direct materials, at the budgeted price of $3 per pound, and 11 hours of direct manufacturing labor, at the budgeted rate of $13 per hour. Following are additional data for the month of July: Units completed 5,600 units,
Direct material purchases 230,000 pounds,
Cost of direct material purchases $759,000,
Actual direct manufacturing labor-hours 43,000 hours,
Actual direct manufacturing labor cost $623,500,
Direct materials efficiency variance $ 1,200 F,
There were no beginning inventories.
1. Compute direct manufacturing labor variances for July,
2. Compute the actual pounds of direct materials used in production in July,
3. Calculate the actual price per pound of direct materials purchased,
4. Calculate the direct materials price variance.

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 16:30, baptistatm51976
Kinda moderates the comments section of an online travel magazine. which type of comments should linda flag or delete as inappropriate content
Answers: 2
image
Business, 21.06.2019 19:40, dlow4974
Policymakers are provided data about the private and social benefits of a good being sold in the market. quantity private mb ($) social mb ($) 6 6 9 7 4 7 8 2 5 9 0 3 what is the size of the externality? if the externality is positive, enter a positive number. if negative, make it a negative number. $ given this data, policymakers must decide whether to address the associated externality with a subsidy or a tax. as their economic consultant, which of the two policy tools would you recommend? a subsidy a tax
Answers: 2
image
Business, 22.06.2019 02:30, llama1314
Sweeten company had no jobs in progress at the beginning of march and no beginning inventories. the company has two manufacturing departments--molding and fabrication. it started, completed, and sold only two jobs during march—job p and job q. the following additional information is available for the company as a whole and for jobs p and q (all data and questions relate to the month of march): molding fabrication total estimated total machine-hours used 2,500 1,500 4,000 estimated total fixed manufacturing overhead $ 10,000 $ 15,000 $ 25,000 estimated variable manufacturing overhead per machine-hour $ 1.40 $ 2.20 job p job q direct materials $ 13,000 $ 8,000 direct labor cost $ 21,000 $ 7,500 actual machine-hours used: molding 1,700 800 fabrication 600 900 total 2,300 1,700 sweeten company had no underapplied or overapplied manufacturing overhead costs during the month. required: for questions 1-8, assume that sweeten company uses a plantwide predetermined overhead rate with machine-hours as the allocation base. for questions 9-15, assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments. 1. what was the company’s plantwide predetermined overhead rate? (round your answer to 2 decimal places.) next
Answers: 2
image
Business, 22.06.2019 10:40, meillsss
Parks corporation is considering an investment proposal in which a working capital investment of $10,000 would be required. the investment would provide cash inflows of $2,000 per year for six years. the working capital would be released for use elsewhere when the project is completed. if the company's discount rate is 10%, the investment's net present value is closest to (ignore income taxes) ?
Answers: 1
You know the right answer?
Direct manufacturing labor and direct materials variances, missing data. (CMA, heavily adapted) Oyst...

Questions in other subjects:

Konu
Mathematics, 28.06.2019 10:00