Consider the following work breakdown structure:What is the probability that this project will be completed within 210 days AND after 195 days? Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic Start A, B,C - - - A D 38 50 62 B E 90 99 108 C E 70 80 90 D E, F 19 25 31 E End 91 100 115 F End 62 65 68 a) 0.815.
b) 0.8413.
c) 0.95.
d) 0.9772.

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 01:00, reagriffis24
How does the economy of cuba differ from the economy of north korea? in north korea, the government’s control of the economy has begun to loosen. in cuba, the government maintains a tight hold over the economy. in cuba, the government’s control of the economy has begun to loosen. in north korea, the government maintains a tight hold over the economy. in north korea, there is economic uncertainty in exchange for individual choice. in cuba, there is economic security in exchange for government control. in cuba, there is economic uncertainty in exchange for individual choice. in north korea, there is economic security in exchange for government control.\
Answers: 2
image
Business, 22.06.2019 11:00, neash19
Why does an organization prepare a balance sheet? a. to reveal what the organization owns and owes at a point in time b. to reveal how well the company utilizes its cash c. to calculate retained earnings for a given accounting period d. to calculate gross profit for a given accounting period
Answers: 3
image
Business, 22.06.2019 20:20, dd123984
Levine inc., which produces a single product, has prepared the following standard cost sheet for one unit of the product. direct materials (9 pounds at $1.80 per pound) $16.20 direct labor (6 hours at $14.00 per hour) $84.00 during the month of april, the company manufactures 270 units and incurs the following actual costs. direct materials purchased and used (2,500 pounds) $5,000 direct labor (1,660 hours) $22,908 compute the total, price, and quantity variances for materials and labor.
Answers: 2
image
Business, 23.06.2019 02:10, jljhenkel
Which of the following best explains the purpose of a supply schedule? a. to calculate how much time it takes for distribution. b. to indicate how supply and demand relate to price. c. to show the relationship between quantity supplied and prices. d. to demonstrate how the supply decreases as price increases.
Answers: 1
You know the right answer?
Consider the following work breakdown structure:What is the probability that this project will be co...

Questions in other subjects:

Konu
Mathematics, 05.03.2021 18:50
Konu
Mathematics, 05.03.2021 18:50