Calculating the Direct Labor Rate Variance and the Direct Labor Efficiency Variance Guillermo's Oil and Lube Company is a service company that offers oil changes and lubrication for automobiles and light trucks. On average, Guillermo has found that a typical oil change takes 18 minutes and 6.2 quarts of oil are used. In June, Guillermo's Oil and Lube had 990 oil changes.
Guillermo's Oil and Lube Company provided the following information for the production of oil changes during the month of June:

Actual number of oil changes performed: 990
Actual number of direct labor hours worked: 291 hours
Actual rate paid per direct labor hour: $16.00
Standard rate per direct labor hour: $15.00

Required:
a. Calculate the direct labor rate variance (LRV) and the direct labor efficiency variance (LEV) for June using the formula approach.
b. Calculate the direct labor rate variance (LRV) and the direct labor efficiency variance (LEV) for June.
c. Calculate the total direct labor variance for oil changes for June.
d. What if the actual wage rate paid in June was $14.00? What impact would that have had on the direct labor rate variance (LRV)? On the direct labor efficiency variance (LEV)? Indicate what the new variances would be below. If required, round your answers to the nearest cent.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 10:00, lm942747
What is the difference between an "i" statement and a "you" statement? a. the "i" statement is non-confrontational b. the "you" statement is non-confrontational c. the "i" statement is argumentative d. the "you" statement is neutral in tone select the best answer from the choices provided
Answers: 1
image
Business, 22.06.2019 12:50, axelsanchez7710
You are working on a bid to build two city parks a year for the next three years. this project requires the purchase of $249,000 of equipment that will be depreciated using straight-line depreciation to a zero book value over the three-year project life. ignore bonus depreciation. the equipment can be sold at the end of the project for $115,000. you will also need $18.000 in net working capital for the duration of the project. the fixed costs will be $37000 a year and the variable costs will be $148,000 per park. your required rate of return is 14 percent and your tax rate is 21 percent. what is the minimal amount you should bid per park? (round your answer to the nearest $100) (a) $214,300 (b) $214,100 (c) $212,500 (d) $208,200 (e) $208,400
Answers: 3
image
Business, 22.06.2019 13:30, karenjunior
Over the past year, three of the star salesmen at family resorts international's corporate office have been lured away to competitors. on top of that, karina, the general manager of the sales department, has noticed that most employees come in, do their jobs, and leave. family resorts offers a good salary, benefits, and tuition reimbursement, as well as a number of development and training programs. most employees seem contented enough, but karina would like to do something to increase the level of engagement among her staff. what do you think karina should do?
Answers: 1
image
Business, 22.06.2019 19:40, madisynk78
Adistinguishing feature of ecological economics is the concept of cost-benefit analysis steady-state economies that, like natural systems, neither grow nor shrink environmental damage and also environmental benefits are external greenwashing to increase public acceptance of products the only healthy economy is one that is growing
Answers: 1
You know the right answer?
Calculating the Direct Labor Rate Variance and the Direct Labor Efficiency Variance Guillermo's Oil...

Questions in other subjects:

Konu
Mathematics, 30.05.2021 14:00