You are calculating the performance of your project. If the actual cost is $80,000, the planned value is $70,000 and the earned value is $65,000, what is the cost performance index?

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 23.06.2019 01:30, goodperson8449
What is the minimum educational requirement for a pediatric psychopharmacologist? a. md b. phd c. bachelors in medicine d. masters in medicine e. psyd
Answers: 1
image
Business, 23.06.2019 03:00, momo1039
By changing its recipe, a smoothie chain is reacting to a change in the environment. while it is important to be able to quickly adapt, it is also important to take a proactive approach to changes in the marketing environment. implementing a proactive approach requires constantly scanning and analyzing the environment so that changes do not come as a surprise. the statements below are findings from environmental scanning and analysis. select the marketing environment force that best describes each of the statements listed.
Answers: 3
image
Business, 23.06.2019 05:30, 24nelsoaddh
What are some examples of types of investments on the part of manufactures that result in growth? how does this improve a nation's standard of living?
Answers: 3
image
Business, 23.06.2019 07:50, lizdeleon248
Three students were applying to the same graduate school. they came from schools with different grading systems. student gpa school average gpa school standard deviation thuy 2.9 3.2 0.8 vichet 83 75 20 kamala 8.6 8 0.4 which student had the best gpa when compared to other students at his school? explain how you determined your answer. (enter your standard deviation to two decimal places.) correct: your answer is correct. had the best gpa compared to other students at his school, since his gpa is 2.25 incorrect: your answer is incorrect. standard deviations correct: your answer is correct. his school's average gpa.
Answers: 3
You know the right answer?
You are calculating the performance of your project. If the actual cost is $80,000, the planned valu...

Questions in other subjects:

Konu
Computers and Technology, 10.01.2021 23:20