Support department cost allocation Blue Mountain Masterpieces produces pictures, paintings, and other home decor. The Printing and Framing production departments are supported by the Janitorial and Security departments. Janitorial costs are allocated to the production departments based on square feet, and security costs are allocated based on asset value. Information about these departments is detailed in the following table:
Janitorial Department Security Department Printing Department Framing Department
Square feet 760 1,040 4,230 4,770
Asset value $900 $1,240 $12,390 $8,610
Department cost $5,200 $6,600 $33,000 $29,000
Management has experimented with different support department cost allocation methods in the past. The different allocation methods did not yield large differences of cost allocation to the production departments.
1. Determine which support department cost allocation method Blue Mountain Masterpieces would most likely use to allocate its support department costs to the production departments.
a. Direct cost allocation method.
b. Sequential cost allocation method.
c. Reciprocal cost allocation method.
d. None of the above.
2. Determine the total costs allocated from each support department to each production department using the method you determined in part (1).
Printing Department Framing Department
Janitorial Department cost allocation $ $
Security Department cost allocation $ $

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 20:00, adriannacomrosenbark
Modern firms increasingly rely on other firms to supply goods and services instead of doing these tasks themselves. this increased level of is leading to increased emphasis on management.
Answers: 2
image
Business, 23.06.2019 01:40, ijohnh14
The new york times (nov. 30, 1993) reported that “the inability of opec to agree last week to cut production has sent the oil market into turmoil . . [leading to] the lowest price for domestic crude oil since june 1990.” why were the members of opec trying to agree to cut production? so they could save more oil for future consumption so they could lower the price so they could raise the price why do you suppose opec was unable to agree on cutting production? because each country has a different production capacity because each country experiences different production costs because each country has an incentive to cheat on any agreement the newspaper also noted opec’s view “that producing nations outside the organization, like norway and britain, should do their share and cut production.” what does the phrase “do their share” suggest about opec’s desired relationship with norway and britain? opec would like norway and britain to keep their production levels high. opec would like norway and britain to act competitively. opec would like norway and britain to join the cartel.
Answers: 2
image
Business, 23.06.2019 13:00, mystury
How should the financial interests of stockholders be balanced with varied interests of stakeholders? if you were writing a code of conduct for your company, how would you address this issue?
Answers: 1
image
Business, 23.06.2019 16:00, gracetay6873
The expenditures and receipts below are related to land, land improvements, and buildings acquired for use in a business enterprise. the receipts are enclosed in parentheses. money borrowed to pay building contractor (signed a note) $(276,500 ) (b) payment for construction from note proceeds 276,500 (c) cost of land fill and clearing 11,220 (d) delinquent real estate taxes on property assumed by purchaser 8,340 (e) premium on 6-month insurance policy during construction 12,060 (f) refund of 1-month insurance premium because construction completed early (2,010 ) (g) architect’s fee on building 27,040 (h) cost of real estate purchased as a plant site (land $206,800 and building $55,900) 262,700 (i) commission fee paid to real estate agency 9,620 (j) installation of fences around property 4,030 (k) cost of razing and removing building 10,130 (l) proceeds from salvage of demolished building (4,910 ) (m) interest paid during construction on money borrowed for construction 13,700 (n) cost of parking lots and driveways 17,690 (o) cost of trees and shrubbery planted (permanent in nature) 14,080 (p) excavation costs for new building 2,950 identify each item by letter and list the items in columnar form.
Answers: 1
You know the right answer?
Support department cost allocation Blue Mountain Masterpieces produces pictures, paintings, and oth...

Questions in other subjects:

Konu
Mathematics, 05.10.2019 05:40
Konu
Mathematics, 05.10.2019 05:40
Konu
Mathematics, 05.10.2019 05:40