Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20
2 - 3 2 60 60
3 1 4 0 70 0
4 1 2 1 50 10
5 2 5 3 100 60
6 3 2 1 90 100
7 4 5 1 50 30
8 5 2 0 60 40
9 6,7,8 3 1 200 200
Consider the project above. If the indirect costs of the project are: $90 at 15 days, $75 at 14 days, $50 at 13 days, $40 at 12 days, and $30 at 11 days.
Please help crash this project in a manner that minimizes the sum of the total direct and indirect costs.
What is the current estimated project duration in days without any crashing?
A. 11
B. 14
C. 13
D. 15

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 01:10, ltawiah8393
Suppose someone wants to sell a piece of land for cash. the selling of a piece of land represents turning econ
Answers: 3
image
Business, 22.06.2019 18:00, judali
David paid $975,000 for two beachfront lots in coastal south carolina, with the intention of building residential homes on each. two years later, the south carolina legislature passed the beachfront management act, barring any further development of the coast, including david's lots. when david files a complaint to seek compensation for his property, south carolina refuses, pointing to a passage in david's own complaint that states "the beachfront management act [was] properly and validly designed to south carolina's " is south carolina required to compensate david under the takings clause?
Answers: 1
image
Business, 23.06.2019 02:00, kyralynn123
You are considering the purchase of one of two machines used in your manufacturing plant. machine 1 has a life of two years, costs $20,000 initially, and then $4,000 per year in maintenance costs. machine 2 costs $25,000 initially, has a life of three years, and requires $3,500 in annual maintenance costs. either machine must be replaced at the end of its life with an equivalent machine. using eac which is the better machine for the firm
Answers: 1
image
Business, 23.06.2019 02:30, PinkyUSA18
Complete electronics inc. sells a point-of-sale computer with a two-year service contract. complete collects $ 2 comma 500 cash for the selling price of the computer and $ 576 for the two-year service contract. how is revenue recognized?
Answers: 2
You know the right answer?
Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20

Questions in other subjects: