Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question. What is the least amount of time that the project can be completed and how many resources are required to complete the work? Task 1 2 workers needed 5 days
Task 2 2 workers needed 3 days Start Project
Task 3 1 worker needed 2 days Finish Project
Task 4 1 worker needed 4 days
Task 5 1 worker needed 2 days
a) 16 days, 7 workers
b) 7 days, 5 workers
c) 5 days, 7 workers
d) 8 days, 3 workers

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 19:00, drey10
Spirula trading inc sublets a part of its offices building to jade inc. for a period of ten years . where will the company disclose this information?
Answers: 3
image
Business, 22.06.2019 17:00, jaymoney0531
Can someone me ? i’ll mark the best answer brainliest : )
Answers: 1
image
Business, 22.06.2019 19:00, whitbol
The demand curve determines equilibrium price in a market. is a graphical representation of the relationship between price and quantity demanded. depicts the relationship between production costs and output. is a graphical representation of the relationship between price and quantity supplied.
Answers: 1
image
Business, 22.06.2019 20:00, krystynas799
In myanmar, six laborers, each making the equivalent of $ 2.50 per day, can produce 40 units per day. in china, ten laborers, each making the equivalent of $ 2.25 per day, can produce 48 units. in billings comma montana, two laborers, each making $ 60.00 per day, can make 102 units. based on labor cost per unit only, the most economical location to produce the item is china , with a labor cost per unit of $ . 05. (enter your response rounded to two decimal places.)
Answers: 3
You know the right answer?
Given this project and the requirement that the number of resources working on a task cannot be less...

Questions in other subjects: