Corporation is a rapidly growing biotech company that has a required rate of return of 14%. It plans to build a new facility in Santa Clara County. The building will take 2 years to complete. The building contractor offered New Pharm a choice of three payment plans, as follows: Plan I: Payment of $ 325,000 at the time of signing the contract and $ 4,825,000 upon completion of the building. The end of the second year is the completion date.
Plan II: Payment of $ 1,675,000 at the time of signing the contract and $ 1,675,000 at the end of each of the 2 succeeding years.
Plan III: Payment of $ 425,000 at the time of signing the contract and $ 1,650,000 at the end of each of the 3 succeeding years.
Required
1. Using the net present value method, calculate the comparative cost of each of the three payment plans being considered by New Tech.
2. Which payment plan should New Tech choose? Explain.
3. Discuss the financial factors, other than the cost of the plan, and the non-financial factors that should be considered in selecting an appropriate payment plan.

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 00:50, emma3216
cranium, inc., purchases term papers from an overseas supplier under a continuous review system. the average demand for a popular mode is 300 units a day with a standard deviation of 30 units a day. it costs $60 to process each order and there is a five−day lead−time. the holding cost for a paper is $0.25 per year and the company policy is to maintain a 98% service level. cranium operates 200 days per year. what is the reorder point r to satisfy a 98% cycleminus−service level? a. greater than 1,700 unitsb. greater than 1,600 units but less than or equal to 1,700 unitsc. greater than 1,500 units but less than or equal to 1,600 unitsd. less than or equal to 1,500 units
Answers: 1
image
Business, 22.06.2019 10:30, batmanmarie2004
The card shoppe needs to maintain 21 percent of its sales in net working capital. currently, the store is considering a four-year project that will increase sales from its current level of $349,000 to $408,000 the first year and to $414,000 a year for the following three years of the project. what amount should be included in the project analysis for net working capital in year 4 of the project?
Answers: 3
image
Business, 22.06.2019 11:00, nathanbrockdac
Using a cps-sample of 7,440 individuals, you estimate the following regression: = 20.91 - 2.61 x female where female is a binary variable that takes on the value of 1 for females and is 0 otherwise. the standard error on the coefficient on female is 0.25. the 95% confidence interval for the gender wage gap, or the amount that females earn less, is: a) [-3.10, -2.12] b) [18.30, 23.52] c) [-3.02, -2.20] d) [-1.96, -1.64]
Answers: 3
image
Business, 22.06.2019 11:10, korban23
Post test question number 9 for entering the job market
Answers: 1
You know the right answer?
Corporation is a rapidly growing biotech company that has a required rate of return of 14%. It plans...

Questions in other subjects:

Konu
English, 06.05.2020 05:15
Konu
Mathematics, 06.05.2020 05:15