Ravelo Corporation has provided the following data from its activity-based costing system: Activity Cost Pools Total Cost Total Activity
Assembly $498,520 44,000 machine-hours
Processing orders $54,263 1,100 orders
Inspection $77,589 1,100 inspection-hours

Data concerning the company's product L19B appear below:

Annual unit production and sales 430
Annual machine-hours 990
Annual number of orders 70
Annual Inspection hours 20
Direct materials cost $37.74 per unit
Direct labor cost $10.45 per unit

According to the activity-based costing system, the average cost of product L19B is closest to:

a. $4819 per unit
b. $82.31 per unit
c. $85.56 per unit
d. $7753 per unit

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 11:40, antbanks3050
Jamie is saving for a trip to europe. she has an existing savings account that earns 3 percent annual interest and has a current balance of $4,200. jamie doesn’t want to use her current savings for vacation, so she decides to borrow the $1,600 she needs for travel expenses. she will repay the loan in exactly one year. the annual interest rate is 6 percent. a. if jamie were to withdraw the $1,600 from her savings account to finance the trip, how much interest would she forgo? .b. if jamie borrows the $1,600 how much will she pay in interest? c. how much does the trip cost her if she borrows rather than dip into her savings?
Answers: 1
image
Business, 22.06.2019 18:50, gucc4836
Retirement investment advisors, inc., has just offered you an annual interest rate of 4.4 percent until you retire in 40 years. you believe that interest rates will increase over the next year and you would be offered 5 percent per year one year from today. if you plan to deposit $13,000 into the account either this year or next year, how much more will you have when you retire if you wait one year to make your deposit?
Answers: 3
image
Business, 22.06.2019 20:10, NorbxrtThaG
Assume that a local bank sells two services, checking accounts and atm card services. the bank’s only two customers are mr. donethat and ms. beenthere. mr. donethat is willing to pay $8 a month for the bank to service his checking account and $2 a month for unlimited use of his atm card. ms. beenthere is willing to pay only $5 for a checking account, but is willing to pay $9 for unlimited use of her atm card. assume that the bank can provide each of these services at zero marginal cost. refer to scenario 17-5. if the bank is unable to use tying, what is the profit-maximizing price to charge for a checking account
Answers: 3
image
Business, 22.06.2019 23:00, tonya3498
Which of the following is not one of the four principles of bottleneck management? a. increasing capacity at non-bottleneck stations is a mirageb. lost time at the bottleneck is lost system capacity. c. release work orders to the system at the bottleneck's capacity pace. d. increased bottleneck capacity is increased system capacity. e. bottlenecks should be moved to the end of the system process.
Answers: 1
You know the right answer?
Ravelo Corporation has provided the following data from its activity-based costing system: Activity...

Questions in other subjects:

Konu
Mathematics, 15.12.2020 04:30
Konu
Mathematics, 15.12.2020 04:30