A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the direct labor efficiency variance

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 08:10, toxsicity
Exercise 15-7 crawford corporation incurred the following transactions. 1. purchased raw materials on account $53,000. 2. raw materials of $45,200 were requisitioned to the factory. an analysis of the materials requisition slips indicated that $9,400 was classified as indirect materials. 3. factory labor costs incurred were $65,400, of which $50,200 pertained to factory wages payable and $15,200 pertained to employer payroll taxes payable. 4. time tickets indicated that $55,000 was direct labor and $10,400 was indirect labor. 5. manufacturing overhead costs incurred on account were $81,700. 6. depreciation on the company’s office building was $8,100. 7. manufacturing overhead was applied at the rate of 160% of direct labor cost. 8. goods costing $89,400 were completed and transferred to finished goods. 9. finished goods costing $76,000 to manufacture were sold on account for $105,100. journalize the transactions. (credit account titles are automatically indented when amount is entered. do not indent manually.) no. account titles and explanation debit credit (1) (2) (3) (4) (5) (6) (7) (8) (9) (to record the sale) (to record the cost of the sale) click if you would like to show work for this question: open show work
Answers: 1
image
Business, 22.06.2019 20:00, tvoalicea
Harry is 25 years old with a 1.55 rating factor for his auto insurance. if his annual base premium is $1,012, what is his total premium? $1,568.60 $2,530 $1,582.55 $1,842.25
Answers: 1
image
Business, 22.06.2019 20:10, janayflowers042
Russell's is considering purchasing $697,400 of equipment for a four-year project. the equipment falls in the five-year macrs class with annual percentages of .2, .32, .192, .1152, .1152, and .0576 for years 1 to 6, respectively. at the end of the project the equipment can be sold for an estimated $135,000. the required return is 13.2 percent and the tax rate is 23 percent. what is the amount of the aftertax salvage value of the equipment assuming no bonus depreciation is taken
Answers: 2
image
Business, 22.06.2019 21:00, neylabaker7489
In a transportation minimization problem, the negative improvement index associated with a cell indicates that reallocating units to that cell would lower costs. truefalse
Answers: 1
You know the right answer?
A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,0...

Questions in other subjects:

Konu
Mathematics, 21.06.2021 20:30
Konu
Mathematics, 21.06.2021 20:30