Kostelnik Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $231,000, variable manufacturing overhead of $2.80 per machine-hour, and 30,000 machine-hours. The company has provided the following data concerning Job A496 which was recently completed:

Number of units in the job 20
Total machine-hour 80
Direct materials $870
Direct labor cost $1,740

The unit product cost for Job A496 is closest to:

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 07:30, QueenNerdy889
1  2  3  4  5  6  7  8  9  10time remaining59: 30in  the dark game, how does the author develop the central idea that elizabeth van lew was a spymaster during the civil war? 1 2 3 4 5 6 7 8 9 10time remaining59: 30in the dark game, how does the author develop the central idea that elizabeth van lew was a spymaster during the civil war?
Answers: 1
image
Business, 22.06.2019 12:50, axelsanchez7710
You are working on a bid to build two city parks a year for the next three years. this project requires the purchase of $249,000 of equipment that will be depreciated using straight-line depreciation to a zero book value over the three-year project life. ignore bonus depreciation. the equipment can be sold at the end of the project for $115,000. you will also need $18.000 in net working capital for the duration of the project. the fixed costs will be $37000 a year and the variable costs will be $148,000 per park. your required rate of return is 14 percent and your tax rate is 21 percent. what is the minimal amount you should bid per park? (round your answer to the nearest $100) (a) $214,300 (b) $214,100 (c) $212,500 (d) $208,200 (e) $208,400
Answers: 3
image
Business, 22.06.2019 18:00, maxout67
*will mark brainliest! * when a company spends resources (labor, money) to give customers "free" items, those costs are called a. investment costs b. economic costs c. scarcity costs d. opportunity costs answer asap!
Answers: 1
image
Business, 22.06.2019 23:30, phillipselijah2
Match the different financial tasks to their corresponding financial life cycle phases wealth protection, wealth accumulation and wealth distribution
Answers: 3
You know the right answer?
Kostelnik Corporation uses a job-order costing system with a single plantwide predetermined overhead...

Questions in other subjects: