A construction company is bidding on a project comprising five high-rise buildings to be erected one after the other. The company considers the purchase of a set of advanced, hydraulically operated tunnel forming systems for $20/sf. The forms are to be used 200 times for the forming of 1,000 sf of walls and 1,000 sf of slabs per use on a series of residential buildings over a period of 4 yr, and then they will be sold. Salvage value is expected to be 10% of original purchase price. No maintenance costs are expected. Labor productivity is estimated at 0.025 labor hr/sf. Hourly wages are $22. Consider 5% annual interest rate. What is the average formwork cost (material

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 19:20, williampagan9532
Which of the following statements is true? a. financial investment refers to the creation and expansion of business enterprisesb. economic investment refers to the creation and expansion of business enterprisesc. economic investment refers to the purchase of assets such as stocks, bonds, and real estated. both economic and financial investment refer to the purchase of assets such as stocks, bonds, and real estate
Answers: 2
image
Business, 22.06.2019 12:00, ddaaaeeee3503
Which of the following is one of the advantages primarily associated with a performance appraisal? (a) it protects employees against discrimination on the basis of race. (b) it motivates employees to work on their shortcomings. (c) it encourages employees to play the role of the whistle-blower. (d) it accurately measures the resources of the firm.
Answers: 2
image
Business, 22.06.2019 17:30, gghkooo1987
An essential element of being receptive to messages is to have an open mind true or false
Answers: 2
image
Business, 22.06.2019 19:40, cieloromero1
Moody corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. at the beginning of the year, the company made the following estimates: machine-hours required to support estimated production 100,000 fixed manufacturing overhead cost $ 650,000 variable manufacturing overhead cost per machine-hour $ 3.00 required: 1. compute the plantwide predetermined overhead rate. 2. during the year, job 400 was started and completed. the following information was available with respect to this job: direct materials $ 450 direct labor cost $ 210 machine-hours used 40
Answers: 3
You know the right answer?
A construction company is bidding on a project comprising five high-rise buildings to be erected one...

Questions in other subjects:

Konu
Chemistry, 15.10.2019 14:50
Konu
Social Studies, 15.10.2019 14:50
Konu
Mathematics, 15.10.2019 14:50