Business, 06.05.2020 02:38 ilovecatsomuchlolol
Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 68% complete. The planners were only expecting to be 55% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,418,500 and it was done for only $1,298,500. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,498,500 but was actually done for $8,998,500. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,498,500. To date they have spent $4,998,500 on the superstructure. Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.) Schedule variance $ Schedule performance index Cost performance index
Answers: 2
Business, 21.06.2019 14:00, ashton3952525
Which is part of the sales process? a. customer retention b. billing c. cost planning d. customer relations
Answers: 1
Business, 22.06.2019 00:20, brainbean
Suppose that the world price of steel is $100 a ton, india does not trade internationally, and the equilibrium price of steel in india is $60 a ton. suppose that india now begins to trade internationally. the price of steel in india the quantity of steel produced in india a. does not change; does not change b. falls; increases c. falls; decreases d. rises; decreases e. rises; increases the quantity of steel bought by india india steel. a. increases; exports b. decreases; imports c. decreases; exports d. does not change; neither imports nor exports e. increases; imports
Answers: 2
Business, 22.06.2019 12:20, ohgeezy
Consider 8.5 percent swiss franc/u. s. dollar dual-currency bonds that pay $666.67 at maturity per sf1,000 of par value. it sells at par. what is the implicit sf/$ exchange rate at maturity? will the investor be better or worse off at maturity if the actual sf/$ exchange rate is sf1.35/$1.00
Answers: 2
Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ah...
Computers and Technology, 01.09.2020 15:01
Spanish, 01.09.2020 15:01
Computers and Technology, 01.09.2020 15:01
Mathematics, 01.09.2020 15:01
Mathematics, 01.09.2020 15:01
Mathematics, 01.09.2020 15:01
Mathematics, 01.09.2020 15:01
Social Studies, 01.09.2020 15:01