Business, 05.05.2020 06:55 sparksjesse2830

A company’s planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the company budgeted the following manufacturing overhead costs: Variable Fixed Indirect materials $50000
Depreciation $37500
Indirect labor 80000
Taxes 7500
Factory supplies 9000
Supervision 30000
A flexible budget prepared at the 90000 machine hours level of activity would show total manufacturing overhead costs of

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 18:20, Heavengunn15
Which of the following is intended to demonstrate to an employer the importance of cooperating with workers? a. a collective agreement. b. a stock offer. c. a boost in production. d. a work slowdown. 2b2t
Answers: 2
image
Business, 22.06.2019 09:30, byron17
Oliver's company is planning the launch of their hybrid cars. the company has included "never-before-seen" product benefits in the hybrid cars. which type of advertising should oliver's company use for the new cars?
Answers: 1
image
Business, 22.06.2019 11:40, lmiranda5034
Zachary company produces commercial gardening equipment. since production is highly automated, the company allocates its overhead costs to product lines using activity-based costing. the costs and cost drivers associated with the four overhead activity cost pools follow: activities unit level batch level product level facility level cost $ 64,800 $ 27,730 $ 15,000 $ 154,000 cost driver 2,400 labor hrs. 47 setups percentage of use 11,000 units production of 780 sets of cutting shears, one of the company’s 20 products, took 240 labor hours and 7 setups and consumed 15 percent of the product-sustaining activities. required: (a) had the company used labor hours as a company wide allocation base, how much overhead would it have allocated to the cutting shears? (b) how much overhead is allocated to the cutting shears using activity-based costing? (c) compute the overhead cost per unit for cutting shears first using activity-based costing and then using direct labor hours for allocation if 780 units are produced. if direct product costs are $150 and the product is priced at 30 percent above cost for what price would the product sell under each allocation system? (d) assuming that activity-based costing provides a more accurate estimate of cost, indicate whether the cutting shears would be over- or underpriced if direct labor hours are used as an allocation base. explain how over-or undercosting can affect vaulker's profitability. (e) comment on the validity of using the allocated facility-level cost in the pricing decision. should other costs be considered in a cost- plus pricing decision? if so, which ones? what costs would you include if you were trying to decide whether to accept a special order?
Answers: 1
image
Business, 22.06.2019 16:00, ari313
What impact might an economic downturn have on a borrower’s fixed-rate mortgage? a. it might cause a borrower’s payments to go up. b. it might cause a borrower’s payments to go down. c. it has no impact because a fixed-rate mortgage cannot change. d. it has no impact because the economy does not affect interest rates.
Answers: 1
You know the right answer?
A company’s planned activity level for next year is expected to be 100000 machine hours. At this lev...

Questions in other subjects:

Konu
Business, 05.04.2021 03:20
Konu
Mathematics, 05.04.2021 03:20
Konu
Mathematics, 05.04.2021 03:20