Collini Corporation has two production departments, Machining and Customizing. The company uses a job-order costing system and computes a predetermined overhead rate in each production department. The Machining Departmentâs predetermined overhead rate is based on machine-hours and the Customizing Departmentâs predetermined overhead rate is based on direct labor-hours. At the beginning of the current year, the company had made the following estimates:

Machining Customizing
Machine-hours 17,000 15,000
Direct labor-hours 3,000 6,000
Total fixed manufacturing overhead cost $102,000 $61,200
Variable manufacturing overhead per machine-hour $ 1.70
Variable manufacturing overhead per direct labor-hour $ 4.10
During the current month the company started and finished Job T268. The following data were recorded for this job:

Job T268: Machining Customizing
Machine-hours 80 30
Direct labor-hours 30 50
Direct materials 720 380
Direct labor cost 900 1,500

If the company marks up its manufacturing costs by 40% then the selling price for Job T268 would be closest to: (Round your intermediate calculations to 2 decimal places.)

A. $6,763.40
B. $7,440.00
C. $4,831.00
D. $1,932.40

ansver
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 15:20, lamashermosa23
On january 2, 2018, bering co. disposes of a machine costing $34,100 with accumulated depreciation of $18,369. prepare the entries to record the disposal under each of the following separate assumptions. exercise 8-24a part 2 2. the machine is traded in for a newer machine having a $50,600 cash price. a $16,238 trade-in allowance is received, and the balance is paid in cash. assume the asset exchange has commercial substance.
Answers: 2
image
Business, 23.06.2019 03:00, yaboi2018
Predict how the price of athletic shorts would change if schools banned their use
Answers: 2
image
Business, 23.06.2019 03:30, audriexpress
What so u want to be when u grow up?
Answers: 1
image
Business, 23.06.2019 09:00, danielahchf
Jorge is attending college next year. he just got information on the college costs and the financial aid package the college is offering. jorge knows his parents can contribute $4,500 each year. jorge’s college costs & financial aid package per year costs financial aid package tuition & fees grants & scholarship $26,000 $18,500 room & board work-study $12,500 $8,500 how much will jorge need to pay each year from his own savings and from loans? $3,000 $7,000 $7,500 $11,500
Answers: 2
You know the right answer?
Collini Corporation has two production departments, Machining and Customizing. The company uses a jo...

Questions in other subjects:

Konu
Mathematics, 08.12.2020 02:30
Konu
Mathematics, 08.12.2020 02:30
Konu
Mathematics, 08.12.2020 02:30
Konu
English, 08.12.2020 02:30
Konu
Spanish, 08.12.2020 02:30