subject
Business, 24.04.2020 19:36 shaylaahayden45061

The company budgeted for production of 3,300 units in June, but actual production was 3,400 units. The company used 33,240 liters of direct material and 320 direct labor-hours to produce this output. The company purchased 35,900 liters of the direct material at $4.90 per liter. The actual direct labor rate was $22.70 per hour and the actual variable overhead rate was $2.70 per hour. The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased. 6. The materials quantity variance for June is:

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 00:30, krystlemiller4307
A) plot the m1 and m2 money stock in the us from 1990-2015. (hint: you may use the data tools provided by fred.) (b) plot the nominal interest rate from 1960 to 2014. (hint: you can either use the daily interest rates for selected u. s. treasury, private money market and capital market instruments from or the effective federal funds rate fromfred.) (c) the consumer price index (cpi) is a measure of the average change over time in the prices paid by urban consumers for a market basket of consumer goods and services. intuitively, the cpi represents the cost of living or the average price level. plot the cpi from 1960 to 2013.(d) the inflation rate is the yearly percentage change in the average price level. in practice, we usually use the percentage change in the cpi to compute the inflation rate. plot the inflation rate from 1960 to 2013.(e) explain the difference between the ex-ante and ex-post real interest rate. use the fisher equation to compute the ex-post real interest rate. plot the nominal interest rate and the ex-post real interest rate from 1960 to 2013 in the same graph.
Answers: 3
image
Business, 22.06.2019 05:50, cdubble04
Which is one solution to levy the complexity of the global matrix strategy with added customer-focused dimensions?
Answers: 3
image
Business, 22.06.2019 08:30, laurabwhiddon
The production manager of rordan corporation has submitted the following quarterly production forecast for the upcoming fiscal year: 1st quarter 2nd quarter 3rd quarter 4th quarter units to be produced 10,800 8,500 7,100 11,200 each unit requires 0.25 direct labor-hours, and direct laborers are paid $20.00 per hour. required: 1. prepare the company’s direct labor budget for the upcoming fiscal year. assume that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced. 2. prepare the company’s direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is not adjusted each quarter. instead, assume that the company’s direct labor workforce consists of permanent employees who are guaranteed to be paid for at least 2,500 hours of work each quarter. if the number of required direct labor-hours is less than this number, the workers are paid for 2,500 hours anyway. any hours worked in excess of 2,500 hours in a quarter are paid at the rate of 1.5 times the normal hourly rate for direct labor.
Answers: 2
image
Business, 22.06.2019 12:50, cece4874
Suppose the real risk-free rate and inflation rate are expected to remain at their current levels throughout the foreseeable future. consider all factors that affect the yield curve. then identify which of the following shapes that the u. s. treasury yield curve can take. check all that apply.
Answers: 2
You know the right answer?
The company budgeted for production of 3,300 units in June, but actual production was 3,400 units. T...