Eaker Company uses activity-based costing to compute product costs for external reports. The company has three activity cost pools and applies overhead using predetermined overhead rates for each activity cost pool. Estimated costs and activities for the current year are presented below for the three activity centres:

Activity Centre Estimated Overhead Costs Expected Activity
Batch setups $20,400 1,200
Material handling 52,800 2,400
General factory 78,000 2,600

Actual costs and activities for the current year were as follows:

Activity Centre Actual Overhead Costs Expected Activity
Batch setups $20,740 1,230
Material handling 52,360 2,470
General factory 77,590 2,680

How much total overhead was applied to products during the year?

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 14:50, arod20061
One pound of material is required for each finished unit. the inventory of materials at the end of each month should equal 20% of the following month's production needs. purchases of raw materials for february would be budgeted to be:
Answers: 2
image
Business, 22.06.2019 15:40, kaitlynmorgan43
The cost of direct labor used in production is recorded as a? a. credit to work-in-process inventory account. b. credit to wages payable. c. credit to manufacturing overhead account. d. credit to wages expense.
Answers: 2
image
Business, 22.06.2019 17:30, gghkooo1987
An essential element of being receptive to messages is to have an open mind true or false
Answers: 2
image
Business, 22.06.2019 19:10, keenansimpkinsoy0oqc
Imagine us is a startup that offers high definition 3d prenatal ultrasounds for high-end customers. the service process includes four activities that are conducted in the sequence described below. (the time required for each activity is shown in parentheses): activity 1: welcome a patient and explain the procedure. (20 minutes)activity 2: prep the patient (e. g., show them to the room, apply ultrasound gel). (17 minutes) (*your id number represents the amount of time needed to complete this task)activity 3: take images. (5 minutes)activity 4: discuss diagnostic with patient. (20 minutes)at each location there are employees (servers) s1, s2, and s3. the assignment of tasks to servers is the following: s1 does activities 1 and 2.s2 does activity 3.s3 does activity 4.a. what is the capacity of this process (in customers per hour)? b. suppose 3 patients arrive every hour on average. ignoring any “start of day” or “end of day” effects, what are the utilizations of all three servers (%)? c. suppose each activity can be done by any server and any server can do any set of activities. however, each activity is done by only one server. for example, a possible assignment includes: s1 does activity 1, s2 does activity 2, and s3 does activities 3 and 4. of course, the original assignment of servers to activities is also feasible. what is the maximum capacity of the process (in customers per hour)? d. now consider the capacity measures in (c) and (a), what is the percentage change? why can you improve capacity without using additional resources? (there is no free lunch, right? )note: for all hw assignments, show your process of getting the results. only providing the final answers is not acceptable and will get 0%. if necessary, use a separate sheet of paper to show your work.
Answers: 3
You know the right answer?
Eaker Company uses activity-based costing to compute product costs for external reports. The company...

Questions in other subjects:

Konu
Mathematics, 25.04.2020 05:07
Konu
Mathematics, 25.04.2020 05:07