Vertis Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. Details for the first quarter of the year are provided here. Choose the correct answer from the options provided.

Days

Wait time 12

Inspection time 0.6

Process time 6

Move time 0.4

Queue time 8

Compute the manufacturing cycle efficiency (MCE).

ansver
Answers: 2

Other questions on the subject: Business

image
Business, 21.06.2019 21:30, cesar566
In its 2016 annual report, caterpillar inc. reported the following (in millions): 2016 2015 sales $38,537 $47,011 cost of goods sold 28,309 33,546 as a percentage of sales, did caterpillar's gross profit increase or decrease during 2016? select one: a. gross profit increased from 26.8% to 28.6% b. gross profit decreased from 28.6% to 26.5% c. gross profit increased from 71.4% to 73.2% d. gross profit decreased from 73.2% to 71.4% e. there is not enough information to answer the question.
Answers: 2
image
Business, 22.06.2019 03:00, sayedaly2096
5. profit maximization and shutting down in the short run suppose that the market for polos is a competitive market. the following graph shows the daily cost curves of a firm operating in this market. 0 2 4 6 8 10 12 14 16 18 20 50 45 40 35 30 25 20 15 10 5 0 price (dollars per polo) quantity (thousands of polos) mc atc avc for each price in the following table, calculate the firm's optimal quantity of units to produce, and determine the profit or loss if it produces at that quantity, using the data from the previous graph to identify its total variable cost. assume that if the firm is indifferent between producing and shutting down, it will produce. (hint: you can select the purple points [diamond symbols] on the previous graph to see precise information on average variable cost.) price quantity total revenue fixed cost variable cost profit (dollars per polo) (polos) (dollars) (dollars) (dollars) (dollars) 12.50 135,000 27.50 135,000 45.00 135,000 if the firm shuts down, it must incur its fixed costs (fc) in the short run. in this case, the firm's fixed cost is $135,000 per day. in other words, if it shuts down, the firm would suffer losses of $135,000 per day until its fixed costs end (such as the expiration of a building lease). this firm's shutdown price—that is, the price below which it is optimal for the firm to shut down—is per polo.
Answers: 3
image
Business, 22.06.2019 07:30, mv603177
Most states have licensing registration requirements for child care centers and family daycare homes. these usually include minimum standard for operation. which of the following would you most likely find required in a statement of state licensing standards for child care centers?
Answers: 2
image
Business, 22.06.2019 11:30, wrivera32802
Leon and sara are arguing over when the best time is to degrease soup. leon says that it's easiest to degrease soup when it's boiling. sara says it's easiest to degrease soup when it's cold. who is correct? a. neither leon nor sara is correct. b. leon is correct. c. both leon and sara are correct. d. sara is correct. student b   incorrect which following answer correct?
Answers: 1
You know the right answer?
Vertis Corporation is interested in cutting the amount of time between when a customer places an ord...

Questions in other subjects:

Konu
Chemistry, 08.02.2021 14:00
Konu
Mathematics, 08.02.2021 14:00
Konu
Mathematics, 08.02.2021 14:00