If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23 days, and $50 for 22 days, compute the direct, indirect, and total costs for each duration. What is the optimum cost-time schedule

ansver
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 15:20, charityclark3935
Assume a firm's production process requires an average of 80 days to go from raw materials to finished products and another 40 days before the finished goods are sold. if the accounts receivable cycle is 70 days and the accounts payable cycle is 80 days, what would the operating cycle be?
Answers: 1
image
Business, 21.06.2019 16:10, allisonhall0925
Reliable electric is a regulated public utility, and it is expected to provide steady dividend growth of 5% per year for the indefinite future. its last dividend was $6 per share; the stock sold for $50 per share just after the dividend was paid. what is the company’s cost of equity? (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places.)
Answers: 2
image
Business, 21.06.2019 19:40, muhammadcorley123456
Anew equipment has been proposed by engineers to increase the productivity of a certain manual welding operation. the investment cost is $25,000, and the equipment will have a market value of $5,000 at the end of a study period of five years. increased productivity attributable to the equipment will amount to $10,000 per year after operating costs have been subtracted from the revenue generated by the additional production. if marr is 10%, is investing in this equipment feasible? use annual worth method.
Answers: 3
image
Business, 21.06.2019 20:30, isidrocastanonox22wl
Monetary policy in the united states is carried out primarily by which of the following agencies? a. the department of the treasury b. the small business association c. the federal reserve bank d. the u. s. mint 2b2t
Answers: 1
You know the right answer?
If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $1...